1575 N HAZELWOOD AVE 90041
Certificate Information: 1575 N HAZELWOOD AVE 90041
- Application / Permit
- 21014-20000-03684
- Plan Check / Job No.
- B21VN09506
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 24' 6" X 28' 8" MASTER BEDROOM/BATHROOM/CLOSET TO REAR OF (E) SFD AND INTERIOR REMODEL TO KITCHEN & (1) BATHROOM. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 7/28/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 6/27/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| Plan Check Approved | 11/3/2022 | ANGELICA MARTINEZ |
| Issued | 12/20/2022 | APPLICANT |
| CofO in Progress | 5/5/2026 | DAVID WILLIAMS |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
| CofO Issued | 5/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 11/2/2021 | JEANIE LAM |
| Sewer availability | Cleared | 11/2/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2021 | JEANIE LAM |
| Trees in Parkway | Cleared | 5/19/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/21/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/24/2022 | AMAAN MALIK |
| Grading Pre-Inspection | Cleared | 11/3/2022 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Djoneva,, Diana Ivanova; Lic. No.: C73805 | 3241 HENRIETTA AVE LA CRESCENTA, CA 91214 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/12/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/18/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/18/2023 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 9/18/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 9/18/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | No Access for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 10/4/2023 | Approved | ROY SPAULDING |
| Gas Test | 10/4/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 10/4/2023 | Corrections Issued | ROY SPAULDING |
| Wood Frame | 10/4/2023 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | No Access for Inspection | ROY SPAULDING |
| Insulation | 10/13/2023 | No Access for Inspection | ROY SPAULDING |
| Interior/Exterior Lathing | 10/13/2023 | Corrections Issued | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Approved | ROY SPAULDING |
| Insulation | 10/17/2023 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 10/17/2023 | Approved | ROY SPAULDING |
| Drywall Nailing | 10/26/2023 | Approved | ROY SPAULDING |
| Shower Pan | 10/26/2023 | Approved | ROY SPAULDING |
| Pre-Inspection | 1/18/2024 | Partial Inspection | AMY COLIN |
| Pre-Inspection | 6/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Pre-Inspection | 8/2/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/4/2026 | Approved | DAVID WILLIAMS |
| Final | 5/4/2026 | OK to Issue CofO | DAVID WILLIAMS |
| Green Building Final | 5/4/2026 | Approved | DAVID WILLIAMS |
| Green Building Rough | 5/4/2026 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 5/4/2026 | Approved | DAVID WILLIAMS |