4747 N SUNNYSLOPE AVE 91423

Certificate Information: 4747 N SUNNYSLOPE AVE 91423

Application / Permit
21014-20000-03679
Plan Check / Job No.
B21VN09486
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12' X 6'-6" COVERED POTCH ADDITION AND 12' X 9' ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 5/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2021 APPLICANT
Assigned to Plan Check Engineer 7/28/2021 JEROME MAGAT PALMA
Corrections Issued 7/28/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 8/21/2021 JEROME MAGAT PALMA
Plan Check Approved 8/30/2021 JEROME MAGAT PALMA
Issued 9/1/2021 APPLICANT
Building Plans Picked Up 9/2/2021 APPLICANT
CofO in Progress 3/8/2022 MISAEL ESPARZA
Permit Finaled 5/14/2022 MICHAEL SMITH
CofO Issued 5/14/2022 MICHAEL SMITH
Permit Finaled 5/14/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/31/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/31/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/2/2021 GABRIEL ROBLES
Sewer availability Cleared 8/2/2021 GABRIEL ROBLES
ZI Cleared 8/16/2021 DANG NGUYEN

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Pro Star Builders Inc; Lic. No.: 1053661-B 17412 VENTURA BLVD SUITE 151      ENCINO, CA 91316

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/18/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/18/2021 Corrections Issued MISAEL ESPARZA
Pre-Inspection 10/18/2021 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 10/20/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 10/25/2021 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/27/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/17/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 11/17/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 11/17/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 11/17/2021 Corrections Issued MISAEL ESPARZA
MERV13>=Rough 11/17/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 11/17/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/19/2021 Partial Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 11/19/2021 Approved ASHLEY THOMPSON
HVAC-Rough 11/19/2021 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 11/24/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/24/2021 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 12/3/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 12/9/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 12/9/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 1/3/2022 Corrections Issued JACK KARGODORIAN
Green Building Rough 1/3/2022 Approved JACK KARGODORIAN
Wood Frame 1/5/2022 Approved MATT KELLERMAN
Drywall Nailing 1/10/2022 Not Ready for Inspection CALEB MEISTER
Drywall Nailing 1/12/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/12/2022 Approved MISAEL ESPARZA
Shower Pan 1/12/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/17/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 2/17/2022 Approved MISAEL ESPARZA
Final 2/17/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 2/17/2022 Approved MISAEL ESPARZA
Green Building Final 2/17/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 2/17/2022 Corrections Issued MISAEL ESPARZA
MERV13>=Final 2/17/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 2/17/2022 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 2/17/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 2/23/2022 Approved MISAEL ESPARZA
Final 2/23/2022 Corrections Issued MISAEL ESPARZA
HVAC-Final 2/23/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 2/23/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 3/1/2022 Approved MISAEL ESPARZA
Final 3/1/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 3/1/2022 Approved MISAEL ESPARZA
HVAC-Final 3/1/2022 Approved MISAEL ESPARZA
MERV13>=Final 3/1/2022 Approved MISAEL ESPARZA
PLUMBING-Final 3/1/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Not Ready MISAEL ESPARZA
Final 3/7/2022 OK to Issue CofO MISAEL ESPARZA
PLUMBING-Final 3/7/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Approved MISAEL ESPARZA