10148 N GLORIA AVE 91343

Certificate Information: 10148 N GLORIA AVE 91343

Application / Permit
21014-20000-03640
Plan Check / Job No.
B21VN09390
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-10" X 26'-6" IRREG SHAPED ADDITIONV TO RELOCATE AND ENLARGE KITCHEN. 19'-7" X 32' IRREG SHAPED ADDITION TO ENLARGE BEDROOMV AND DINING ROOM. REFRAME ROOF OF (E) SINGLE FAMILY DWELLING W/ ATT GARAGE. (NFPA 13D FIRE SPRINKLERS REQUIRED)
Permit Issued
Issued on 2/2/2022
Issuing Office
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2021 APPLICANT
Assigned to Plan Check Engineer 7/27/2021 JEROME MAGAT PALMA
Corrections Issued 7/27/2021 JEROME MAGAT PALMA
Plan Check Approved 2/2/2022 JEROME MAGAT PALMA
Issued 2/2/2022 APPLICANT
Building Plans Picked Up 2/3/2022 APPLICANT
CofO in Progress 7/26/2023 JAVIER RAMOS JR
Permit Finaled 8/30/2023 RUBEN SALAS
CofO Issued 8/30/2023 RUBEN SALAS
Permit Finaled 8/30/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/3/2021 CARLOS AGUILERA
Sewer availability Cleared 8/3/2021 CARLOS AGUILERA
Low Impact Development Cleared 10/21/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 11/15/2021 CARLOS AGUILERA
GPI Written Notices Cleared 11/22/2021 JEROME MAGAT PALMA
Grading Pre-Inspection Cleared 11/22/2021 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/2/2022 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 3/7/2022 Approved MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/25/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 3/30/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 3/30/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval JAVIER RAMOS JR
Insulation 4/5/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/25/2022 Approved JAVIER RAMOS JR
HVAC-Rough 5/25/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/25/2022 Approved JAVIER RAMOS JR
Wood Frame 5/25/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 6/9/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/9/2022 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 6/9/2022 Approved JAVIER RAMOS JR
Wood Frame 6/9/2022 Approved JAVIER RAMOS JR
Insulation 6/22/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/22/2022 Not Ready for Inspection JAVIER RAMOS JR
Shower Pan 6/22/2022 Approved JAVIER RAMOS JR
Drywall Nailing 7/1/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/1/2022 Approved JAVIER RAMOS JR
Special/Order Compliance 10/17/2022 Partial Inspection ROBERT GOLD
Special/Order Compliance 10/18/2022 Corrections Issued ROBERT GOLD
ELECTRICAL-Final 6/27/2023 Approved JAVIER RAMOS JR
Final 6/27/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 6/27/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/27/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/21/2023 Approved JAVIER RAMOS JR
Final 7/21/2023 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 7/21/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 7/26/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 7/26/2023 Approved JAVIER RAMOS JR