10148 N GLORIA AVE 91343
Certificate Information: 10148 N GLORIA AVE 91343
- Application / Permit
- 21014-20000-03640
- Plan Check / Job No.
- B21VN09390
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 22'-10" X 26'-6" IRREG SHAPED ADDITIONV TO RELOCATE AND ENLARGE KITCHEN. 19'-7" X 32' IRREG SHAPED ADDITION TO ENLARGE BEDROOMV AND DINING ROOM. REFRAME ROOF OF (E) SINGLE FAMILY DWELLING W/ ATT GARAGE. (NFPA 13D FIRE SPRINKLERS REQUIRED)
- Permit Issued
- Issued on 2/2/2022
- Issuing Office
- Current Status
- CofO Issued on 8/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 7/27/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/2/2022 | JEROME MAGAT PALMA |
| Issued | 2/2/2022 | APPLICANT |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| CofO in Progress | 7/26/2023 | JAVIER RAMOS JR |
| Permit Finaled | 8/30/2023 | RUBEN SALAS |
| CofO Issued | 8/30/2023 | RUBEN SALAS |
| Permit Finaled | 8/30/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/3/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/21/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 11/15/2021 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 11/22/2021 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 11/22/2021 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/2/2022 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 3/7/2022 | Approved | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/25/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/30/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/30/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 4/5/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/25/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/25/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/25/2022 | Approved | JAVIER RAMOS JR |
| Wood Frame | 5/25/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 6/9/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/9/2022 | Partial Approval | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 6/9/2022 | Approved | JAVIER RAMOS JR |
| Wood Frame | 6/9/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/22/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/22/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Shower Pan | 6/22/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/1/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/1/2022 | Approved | JAVIER RAMOS JR |
| Special/Order Compliance | 10/17/2022 | Partial Inspection | ROBERT GOLD |
| Special/Order Compliance | 10/18/2022 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Final | 6/27/2023 | Approved | JAVIER RAMOS JR |
| Final | 6/27/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 6/27/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 6/27/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/21/2023 | Approved | JAVIER RAMOS JR |
| Final | 7/21/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 7/21/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 7/26/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 7/26/2023 | Approved | JAVIER RAMOS JR |