6540 N LINDLEY AVE 91335
Certificate Information: 6540 N LINDLEY AVE 91335
- Application / Permit
- 21014-20000-03611
- Plan Check / Job No.
- B21VN09313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTERIOR ALTERATION TO REMOVE THE (E) PATIO COVER AND ADDITION OF 20'-8" x 21' TO THE REAR OF THE (E) SINGLE-FAMILY DWELLING. ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/6/2022
- Issuing Office
- Current Status
- Issued on 4/6/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2021 | LUIS RINCON |
| Corrections Issued | 8/21/2021 | LUIS RINCON |
| Applicant returned to address corrections | 10/15/2021 | LUIS RINCON |
| Applicant returned to address corrections | 2/4/2022 | LUIS RINCON |
| Plan Check Approved | 3/23/2022 | OMAR GARNICA |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| Issued | 4/6/2022 | APPLICANT |
| Refund in Progress-Status Void | 5/24/2022 | SELENIA GARCIA |
| Re-Activate Permit | 5/25/2022 | MARY SUM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 2/28/2022 | JOSE DUARTE-DIAZ |
| ZI | Cleared | 3/4/2022 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/18/2022 | Partial Inspection | ROBERT GOLD |
| Deputy Drilled-In Anchors | 5/3/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/11/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/23/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 5/23/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 7/11/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 7/11/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 7/11/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 7/11/2022 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Approved | JEFFREY BULL |
| Insulation | 7/19/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 7/19/2022 | Partial Approval | JEFFREY BULL |
| Shower Pan | 7/19/2022 | Approved | JEFFREY BULL |
| Drywall Nailing | 8/5/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/5/2022 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 8/5/2022 | Approved | JUSTIN HAWLEY |
| Final | 10/17/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 10/17/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 10/17/2022 | Approved | TROY SANDERS |
| Final | 1/19/2023 | Not Ready for Inspection | JEFFREY BULL |
| Service/Power Release | 1/19/2023 | Approved | JEFFREY BULL |