5716 N NOBLE AVE 91411
Certificate Information: 5716 N NOBLE AVE 91411
- Application / Permit
- 21014-20000-03609
- Plan Check / Job No.
- B21VN09310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRR. SHAPED ADDITION AT FRONT AND REAR (1,120 SF IN TOTAL) OF (E) SINFLE FAMILY DWELLING, INTERIOR REMODEL AND ADD 2 NEW ATT. OPEN DECKS; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 3/31/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | SEAN SHAHMIRI |
| Corrections Issued | 8/14/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 8/18/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/20/2021 | APPLICANT |
| Applicant returned to address corrections | 2/14/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 3/7/2022 | SEAN SHAHMIRI |
| Issued | 3/31/2022 | APPLICANT |
| CofO in Progress | 6/3/2024 | RYAN SALAZAR |
| CofO Issued | 8/5/2024 | RUBEN SALAS |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/13/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/18/2022 | ANTHONY VARGAS |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/3/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Builders Hub Renovation Inc; Lic. No.: 1063741-B | 14622 VENTURA BLVD STE 102 SHERMAN OAKS, CA 91403 |
| Engineer | Sabzehzar,, Habib; Lic. No.: C50442 | 8180 N PRICE AVE FRESNO, CA 93720 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/19/2022 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 8/15/2022 | Approved | RICHARD DOCKUS |
| Sewer | 10/24/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 11/17/2022 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 11/17/2022 | Partial Approval | RICHARD DOCKUS |
| Insulation | 11/22/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | No Access for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 2/6/2023 | Partial Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/19/2023 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/19/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/19/2023 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 5/19/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/5/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/5/2023 | Approved | RYAN SALAZAR |
| Insulation | 7/5/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/10/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 7/10/2023 | Approved | RYAN SALAZAR |
| Gas Test | 3/1/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 4/11/2024 | Approved | RYAN SALAZAR |
| Final | 4/11/2024 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 4/11/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 4/11/2024 | Approved | RYAN SALAZAR |
| Final | 5/2/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 5/2/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 5/16/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 5/16/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 5/28/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 5/28/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 5/28/2024 | Approved | RYAN SALAZAR |