8311 S CAMPION DR 90045
Certificate Information: 8311 S CAMPION DR 90045
- Application / Permit
- 21014-20000-03593
- Plan Check / Job No.
- B21VN09253
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 6'-6" X 21'ADDITION TO THE (E) SINGLE FAMILY DWELLING TO EXPAND THE (E) KITCHEN AND ADD A BATHROOM.
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- CofO Issued on 10/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2021 | SERGIO MUNIZ |
| Corrections Issued | 7/21/2021 | SERGIO MUNIZ |
| Plan Check Approved | 9/3/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 11/16/2021 | APPLICANT |
| Issued | 11/22/2021 | APPLICANT |
| CofO in Progress | 10/13/2023 | BOBBY KEY |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| CofO Issued | 10/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/6/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2021 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 8/26/2021 | PEDRO AYALA |
Contact Information
| Architect | Huddy,, Robert Francis; Lic. No.: C20474 | 3648 GOODLAND DR STUDIO CITY, CA 91604 |
| Contractor | Zetino And Son'S Construction; Lic. No.: 817787-B | 841 S CALIFORNIA AVE WEST COVINA, CA 91790 |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 12/7/2021 | Corrections Issued | DAVID FEILER |
| METHANE-Barrier | 12/7/2021 | Approved | DAVID FEILER |
| METHANE-Subgrade | 12/7/2021 | Approved | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 12/13/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 12/23/2021 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 2/28/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/28/2022 | Approved | RYAN SALAZAR |
| Wood Frame | 2/28/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/31/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/5/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Approved | BOBBY KEY |
| Green Building Rough | 4/5/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 4/5/2022 | Corrections Issued | BOBBY KEY |
| Insulation | 4/5/2022 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 4/11/2022 | Approved | RYAN SALAZAR |
| Gas Test | 5/4/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 5/4/2022 | Approved | BOBBY KEY |
| Shower Pan | 5/4/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Not Ready | BOBBY KEY |
| ELECTRICAL-Final | 12/16/2022 | Approved | BOBBY KEY |
| Final | 12/16/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 12/16/2022 | Approved | BOBBY KEY |
| HVAC-Final | 12/16/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 12/16/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 12/16/2022 | Approved | BOBBY KEY |
| Final | 9/27/2023 | Corrections Issued | BOBBY KEY |
| Gas Test | 9/27/2023 | Approved | BOBBY KEY |
| HVAC-Final | 9/27/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | BOBBY KEY |
| Gas Test | 10/4/2023 | Approved | TEMISTOCLES CAAL |
| Final | 10/13/2023 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/13/2023 | SGSOV Approved | BOBBY KEY |