15740 W MAYALL ST 91343
Certificate Information: 15740 W MAYALL ST 91343
- Application / Permit
- 21014-20000-03582
- Plan Check / Job No.
- B21VN09233
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert Existing Garage & storage to ADU WITH AN ADDITION PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 8/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | CARLOS MONTES |
| Corrections Issued | 7/30/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 8/23/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/3/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/10/2021 | CARLOS MONTES |
| Plan Check Approved | 12/17/2021 | CARLOS MONTES |
| Issued | 1/12/2022 | APPLICANT |
| CofO in Progress | 8/23/2023 | ROBERT GOLD |
| Permit Finaled | 8/25/2023 | RUBEN SALAS |
| Permit Finaled | 8/25/2023 | RUBEN SALAS |
| CofO Issued | 8/25/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/31/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/2/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/2/2021 | LEE GUILBEAUX |
| Hold | Cleared | 8/18/2021 | JASON SHEETS |
| Construction near power lines | Cleared | 11/24/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| Underground Mechanical | 2/9/2022 | Partial Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 3/1/2022 | Conditional Approval | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 3/4/2022 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/4/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 3/15/2022 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/15/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Deputy Drilled-In Anchors | 8/26/2022 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 9/6/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2022 | Approved | SEAN WIRCH |
| Green Building Rough | 9/6/2022 | Approved | SEAN WIRCH |
| MERV13>=Rough | 9/6/2022 | Approved | SEAN WIRCH |
| Rough-Elec/Plmb/HVAC | 9/6/2022 | Approved | SEAN WIRCH |
| Sewer | 9/6/2022 | Approved | SEAN WIRCH |
| Insulation | 9/16/2022 | Partial Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/16/2022 | Partial Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 9/16/2022 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 9/19/2022 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 9/19/2022 | Approved | SEAN WIRCH |
| Underground Mechanical | 9/19/2022 | Approved | SEAN WIRCH |
| Drywall Nailing | 9/23/2022 | Approved | SEAN WIRCH |
| Final | 3/31/2023 | Not Ready for Inspection | ROBERT GOLD |
| Footing/Foundation/Slab | 3/31/2023 | Partial Inspection | ROBERT GOLD |
| Green Building Final | 3/31/2023 | Approved | ROBERT GOLD |
| MERV13>=Final | 3/31/2023 | Not Ready for Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 3/31/2023 | Approved | ROBERT GOLD |
| Final | 8/15/2023 | OK to Issue CofO | ROBERT GOLD |
| Footing/Foundation/Slab | 8/15/2023 | Approved | ROBERT GOLD |
| MERV13>=Final | 8/15/2023 | Approved | ROBERT GOLD |