14951 W CHATSWORTH DR 91345
Certificate Information: 14951 W CHATSWORTH DR 91345
- Application / Permit
- 21014-20000-03553
- Plan Check / Job No.
- B21VN09137
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT WITH 1ST AND 2ND STORY ADDITION PER LAMC 12.22A33 (c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/19/2022
- Issuing Office
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | COLIN LOREDO |
| Corrections Issued | 8/24/2021 | COLIN LOREDO |
| Quality Review Completed | 9/7/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| Plan Check Approved | 1/13/2022 | COLIN LOREDO |
| Issued | 1/19/2022 | APPLICANT |
| CofO in Progress | 7/7/2022 | JENNIFER RABUCHIN |
| CofO Issued | 7/14/2022 | MICHAEL SMITH |
| Permit Finaled | 7/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/31/2021 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 9/14/2021 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 1/10/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/11/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/11/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/11/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/11/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 3/11/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 3/11/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 3/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 3/11/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 3/11/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 3/18/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 3/18/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| Sewer | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/31/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 3/31/2022 | Approved | DEANDRE HOFFMAN |
| Shower Pan | 3/31/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 4/7/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/7/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 6/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/17/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 6/17/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 6/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 6/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/17/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 6/17/2022 | Approved | JENNIFER RABUCHIN |
| Final | 6/29/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Gas Test | 6/29/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 6/29/2022 | Approved | MATTHEW NELSON |
| MERV13>=Final | 6/29/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 6/29/2022 | Approved | MATTHEW NELSON |
| Service/Power Release | 6/29/2022 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 7/7/2022 | Approved | JENNIFER RABUCHIN |
| Final | 7/7/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 7/7/2022 | Approved | JENNIFER RABUCHIN |