6517 N WILKINSON AVE 91606

Certificate Information: 6517 N WILKINSON AVE 91606

Application / Permit
21014-20000-03552
Plan Check / Job No.
B21VN09135
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR REMODEL REMOVING ALL WALLS EXCEPT FOR ATTACHED GARAGE AND 23'-0" OF WALL ON NORTH WALL; 1148 SQFT ADDITION W/NEW 485 SQFT COVERED PATIO TO EXISTING SINGLE FAMILY DWELLING (57'-0"x57'-7") W/ NFPA13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
Issued on 4/22/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 PETER MOSESIAN
Corrections Issued 8/14/2021 PETER MOSESIAN
Quality Review Completed 8/26/2021 OMID HEDAYAT
Building Plans Picked Up 9/1/2021 APPLICANT
Plan Check Approved 3/17/2022 PETER MOSESIAN
Issued 4/22/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 8/20/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/21/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/31/2022 MATTHEW CRAIG
Low Impact Development Cleared 2/18/2022 NICK RAYGOZA
Roof/Waste drainage to street Cleared 2/24/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/18/2022 Approved WILLIAM WREN
PLUMBING-Rough 11/21/2022 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval JORDAN KUTZLY
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/27/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 2/27/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 2/27/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 2/27/2023 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 2/27/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 2/27/2023 Partial Approval MICHEL ABAJAN
Shower Pan 2/27/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/22/2023 Not Ready for Inspection KIRK SANDERS
Green Building Rough 3/22/2023 Approved KIRK SANDERS
HVAC-Rough 3/22/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 3/22/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 3/29/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 3/29/2023 Corrections Issued MISAEL ESPARZA
HVAC-Rough 3/29/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 5/1/2023 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 5/1/2023 Corrections Issued WILLIAM WREN
Verify Sprinkler Sign Off 5/1/2023 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 5/8/2023 Conditional Approval KIRK SANDERS
PLUMBING-Rough 5/8/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 5/8/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/10/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Approved KIRK SANDERS
Insulation 5/18/2023 Approved KIRK SANDERS
Drywall Nailing 6/2/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 8/15/2023 Approved KIRK SANDERS
Final 11/16/2023 Corrections Issued KIRK SANDERS
Green Building Final 11/16/2023 Not Ready for Inspection KIRK SANDERS
MERV13>=Final 11/16/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 11/16/2023 Corrections Issued KIRK SANDERS
Final 12/19/2023 Corrections Issued JOSE AVILA
Gas Test 12/19/2023 Approved JOSE AVILA
Green Building Final 12/19/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Not Ready JOSE AVILA
Smoke Detectors 12/19/2023 Approved JOSE AVILA
ELECTRICAL-Final 12/22/2023 Approved JOSE AVILA
Gas Test 12/22/2023 Approved JOSE AVILA
HVAC-Final 12/22/2023 Approved JOSE AVILA
PLUMBING-Final 12/22/2023 Approved JOSE AVILA
Final 4/29/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Not Ready JOSE AVILA