6517 N WILKINSON AVE 91606
Certificate Information: 6517 N WILKINSON AVE 91606
- Application / Permit
- 21014-20000-03552
- Plan Check / Job No.
- B21VN09135
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL REMOVING ALL WALLS EXCEPT FOR ATTACHED GARAGE AND 23'-0" OF WALL ON NORTH WALL; 1148 SQFT ADDITION W/NEW 485 SQFT COVERED PATIO TO EXISTING SINGLE FAMILY DWELLING (57'-0"x57'-7") W/ NFPA13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- Issued on 4/22/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | PETER MOSESIAN |
| Corrections Issued | 8/14/2021 | PETER MOSESIAN |
| Quality Review Completed | 8/26/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/1/2021 | APPLICANT |
| Plan Check Approved | 3/17/2022 | PETER MOSESIAN |
| Issued | 4/22/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/20/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/31/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/18/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 2/24/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2022 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 11/21/2022 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Partial Approval | JORDAN KUTZLY |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/27/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/27/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 2/27/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 2/27/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 2/27/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/27/2023 | Partial Approval | MICHEL ABAJAN |
| Shower Pan | 2/27/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/22/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 3/22/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 3/22/2023 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 3/22/2023 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/29/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/29/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 3/29/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/1/2023 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 5/1/2023 | Corrections Issued | WILLIAM WREN |
| Verify Sprinkler Sign Off | 5/1/2023 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 5/8/2023 | Conditional Approval | KIRK SANDERS |
| PLUMBING-Rough | 5/8/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 5/8/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Approved | KIRK SANDERS |
| Insulation | 5/18/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 6/2/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 8/15/2023 | Approved | KIRK SANDERS |
| Final | 11/16/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 11/16/2023 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Final | 11/16/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 11/16/2023 | Corrections Issued | KIRK SANDERS |
| Final | 12/19/2023 | Corrections Issued | JOSE AVILA |
| Gas Test | 12/19/2023 | Approved | JOSE AVILA |
| Green Building Final | 12/19/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 12/19/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/22/2023 | Approved | JOSE AVILA |
| Gas Test | 12/22/2023 | Approved | JOSE AVILA |
| HVAC-Final | 12/22/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/22/2023 | Approved | JOSE AVILA |
| Final | 4/29/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 4/29/2024 | SGSOV Not Ready | JOSE AVILA |