3101 S STANFORD AVE 90292
Certificate Information: 3101 S STANFORD AVE 90292
- Application / Permit
- 21014-20000-03551
- Plan Check / Job No.
- B21VN09130
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 22'-7" X 11' ADDITION TO THE REAR OF THE (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 6/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2021 | OMAR GARNICA |
| Corrections Issued | 7/15/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 11/18/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 2/22/2022 | OMAR GARNICA |
| Plan Check Approved | 2/23/2022 | OMAR GARNICA |
| Building Plans Picked Up | 3/1/2022 | APPLICANT |
| Issued | 3/17/2022 | APPLICANT |
| CofO in Progress | 6/2/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 6/5/2023 | DANIEL ORRANTE |
| CofO Issued | 6/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 11/19/2021 | LAUREN PADICK |
| Specific Plan | Cleared | 12/5/2021 | EDUARDO HERMOSO |
| Specific Plan | Cleared | 1/18/2022 | IRA BROWN |
| Specific Plan | Cleared | 1/18/2022 | IRA BROWN |
| Roof/Waste drainage to street | Cleared | 2/7/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Bela Development; Lic. No.: 1038287-B | 1023 1/2 ABBOT KINNEY BLVD VENICE, CA 90291 |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/22/2022 | Corrections Issued | PATRICK QUALEY |
| METHANE-Barrier | 3/22/2022 | Approved | PATRICK QUALEY |
| METHANE-Subgrade | 3/22/2022 | Approved | PATRICK QUALEY |
| Footing/Foundation/Slab | 3/24/2022 | Approved | PATRICK QUALEY |
| BUILDING-Rough-Frame | 4/6/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/6/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/8/2022 | Partial Approval | PATRICK QUALEY |
| PLUMBING-Rough | 4/8/2022 | Partial Approval | PATRICK QUALEY |
| ELECTRICAL-Rough | 5/3/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | PATRICK QUALEY |
| PLUMBING-Rough | 5/3/2022 | Not Ready for Inspection | PATRICK QUALEY |
| BUILDING-Rough-Frame | 5/17/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Green Building Rough | 5/17/2022 | Not Ready for Inspection | PATRICK QUALEY |
| METHANE-Rough | 5/17/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 5/17/2022 | Corrections Issued | PATRICK QUALEY |
| Wood Frame | 5/17/2022 | Corrections Issued | PATRICK QUALEY |
| Rough-Elec/Plmb/HVAC | 5/24/2022 | Approved | PATRICK QUALEY |
| Wood Frame | 5/24/2022 | Approved | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/1/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 6/1/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/3/2022 | Approved | PATRICK QUALEY |
| Insulation | 6/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 6/21/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/21/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/21/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 10/13/2022 | Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 4/6/2023 | Not Ready for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/1/2023 | Approved | JESUS RODRIGUEZ |
| Final | 6/1/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 6/1/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/1/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/1/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 6/1/2023 | Approved | JESUS RODRIGUEZ |