9921-9923 N LEMONA AVE 91345
Certificate Information: 9921-9923 N LEMONA AVE 91345
- Application / Permit
- 21014-20000-03535
- Plan Check / Job No.
- B21VN09082
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 495 S.F. attached Accessory Dwelling Unit (ADU) and addition of 445 S.F. exterior patio cover to an existing single family dwelling.
- Permit Issued
- Issued on 4/2/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2021 | JOE VO |
| Corrections Issued | 7/16/2021 | JOE VO |
| Applicant returned to address corrections | 11/25/2021 | JOE VO |
| Plan Check Approved | 3/22/2022 | JOE VO |
| Issued | 4/2/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 11/30/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/11/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/21/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/21/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/27/2022 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 6/30/2022 | Partial Approval | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/18/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/18/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 7/18/2022 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 7/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 7/20/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 7/20/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/22/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/22/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/31/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/31/2022 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 8/31/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/12/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/12/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/15/2022 | Approved | JENNIFER RABUCHIN |
| Final | 11/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/15/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 11/15/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/22/2023 | Approved | JENNIFER RABUCHIN |
| Final | 2/22/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 2/22/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 2/22/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/22/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 2/22/2023 | Approved | JENNIFER RABUCHIN |