20719-20723 W CLARK ST 91367

Certificate Information: 20719-20723 W CLARK ST 91367

Application / Permit
21014-20000-03533
Plan Check / Job No.
B21VN09080
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADU ADDITION TO AN (E) SFD FOR AN ATTACHED ADU PER ORDINANCE (1-STORY ) ***ADU PER ORDINANCE IS NOT ALLOWED WITH A JADU
Permit Issued
Issued on 12/30/2021
Issuing Office
Current Status
CofO Issued on 6/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 CARLOS MONTES
Corrections Issued 7/15/2021 CARLOS MONTES
Applicant returned to address corrections 11/23/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 12/10/2021 CARLOS MONTES
Plan Check Approved 12/23/2021 CARLOS MONTES
Issued 12/30/2021 APPLICANT
CofO in Progress 6/27/2022 STEVEN BACK
Permit Finaled 6/28/2022 JOHN JANSON
CofO Issued 6/28/2022 JOHN JANSON
Permit Finaled 6/28/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/19/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/21/2021 CARLOS AGUILERA
Sewer availability Cleared 7/21/2021 CARLOS AGUILERA
Miscellaneous Cleared 8/10/2021 DANG NGUYEN
Construction near power lines Cleared 9/8/2021 WALTER RAMIREZ
Hydrant and Access approval Cleared 10/2/2021 RUEL COLE
Low Impact Development Cleared 10/6/2021 TA ANH
Roof/Waste drainage to street Cleared 10/6/2021 CARLOS AGUILERA
GPI Written Notices Cleared 12/12/2021 CARLOS MONTES
Grading Pre-Inspection Cleared 12/12/2021 CARLOS MONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/14/2022 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 1/18/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 1/18/2022 Not Ready for Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 1/21/2022 Approved STEVEN BACK
Footing/Foundation/Slab 1/21/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/14/2022 Approved STEVEN BACK
ELECTRICAL-Rough 3/2/2022 Approved STEVEN BACK
HVAC-Rough 3/2/2022 Approved STEVEN BACK
Interior/Exterior Lathing 3/2/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 3/2/2022 Approved STEVEN BACK
Sewer 3/2/2022 Approved STEVEN BACK
Underground Mechanical 3/2/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 3/8/2022 Approved STEVEN BACK
Insulation 3/8/2022 Approved STEVEN BACK
Interior/Exterior Lathing 3/8/2022 Approved STEVEN BACK
MERV13>=Rough 3/8/2022 Approved STEVEN BACK
Drywall Nailing 3/14/2022 Approved MORRIS JACKSON
Special/Order Compliance 3/16/2022 Partial Inspection STEVEN BACK
ELECTRICAL-Final 6/27/2022 Approved STEVEN BACK
Final 6/27/2022 OK to Issue CofO STEVEN BACK
HVAC-Final 6/27/2022 Approved STEVEN BACK
MERV13>=Final 6/27/2022 Approved STEVEN BACK
PLUMBING-Final 6/27/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/27/2022 SGSOV Approved STEVEN BACK
Smoke Detectors 6/27/2022 Approved STEVEN BACK