6700 N ST CLAIR AVE 91606

Certificate Information: 6700 N ST CLAIR AVE 91606

Application / Permit
21014-20000-03531
Plan Check / Job No.
B21VN09078
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Addition to and conversion of the exiting detached garage to a new Accessory Dwelling Unit. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 9/10/2021
Issuing Office
Current Status
CofO Issued on 9/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 HERNAN ARREOLA
Corrections Issued 7/15/2021 HERNAN ARREOLA
Plan Check Approved 9/8/2021 HERNAN ARREOLA
Issued 9/10/2021 APPLICANT
CofO in Progress 8/31/2022 RAFAEL CORTES
CofO Issued 9/6/2022 MICHAEL SMITH
Permit Finaled 9/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/16/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/11/2021 GABRIEL ROBLES
Sewer availability Cleared 8/11/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/30/2021 LEE GUILBEAUX
Redevelopment Project Area Cleared 9/3/2021 GRACIELA ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/17/2021 Partial Approval DANIEL DREW
BUILDING-Rough-Frame 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 9/20/2021 No Access for Inspection CHRISTOPHE COCHRAN
Drywall Nailing 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Final 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Rough 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Final 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Not Ready CHRISTOPHE COCHRAN
Service/Power Release 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 9/20/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 9/23/2021 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/23/2021 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 9/24/2021 Conditional Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/16/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/16/2021 Approved CHRISTOPHE COCHRAN
HVAC-Rough 11/16/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/16/2021 Partial Approval CHRISTOPHE COCHRAN
MERV13>=Rough 11/16/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 11/16/2021 Approved CHRISTOPHE COCHRAN
Underground Mechanical 11/16/2021 Approved CHRISTOPHE COCHRAN
Insulation 11/19/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/19/2021 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 11/19/2021 Approved ASHLEY THOMPSON
Drywall Nailing 11/23/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/23/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Final 2/2/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 2/2/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 2/2/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/21/2022 Corrections Issued RAFAEL CORTES
Final 7/21/2022 Corrections Issued RAFAEL CORTES
HVAC-Final 7/21/2022 Not Ready for Inspection RAFAEL CORTES
MERV13>=Final 7/21/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Final 7/21/2022 Corrections Issued RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 7/21/2022 Approved RAFAEL CORTES
ELECTRICAL-Final 7/26/2022 Corrections Issued RAFAEL CORTES
Final 7/26/2022 Not Ready for Inspection RAFAEL CORTES
HVAC-Final 7/26/2022 Corrections Issued RAFAEL CORTES
MERV13>=Final 7/26/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Final 7/26/2022 Corrections Issued RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 7/26/2022 SGSOV Approved RAFAEL CORTES
ELECTRICAL-Final 8/3/2022 Not Ready for Inspection RAFAEL CORTES
Final 8/3/2022 Not Ready for Inspection RAFAEL CORTES
HVAC-Final 8/3/2022 Not Ready for Inspection RAFAEL CORTES
MERV13>=Final 8/3/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Final 8/3/2022 Not Ready for Inspection RAFAEL CORTES
ELECTRICAL-Final 8/11/2022 Approved RAFAEL CORTES
HVAC-Final 8/11/2022 Corrections Issued RAFAEL CORTES
PLUMBING-Final 8/11/2022 Approved RAFAEL CORTES
Pre-Inspection 8/11/2022 Approved RAFAEL CORTES
ELECTRICAL-Final 8/30/2022 Approved RAFAEL CORTES
Final 8/30/2022 OK to Issue CofO RAFAEL CORTES
HVAC-Final 8/30/2022 Approved RAFAEL CORTES
MERV13>=Final 8/30/2022 Approved RAFAEL CORTES
PLUMBING-Final 8/30/2022 Approved RAFAEL CORTES