13424 W DEBBY ST 91401

Certificate Information: 13424 W DEBBY ST 91401

Application / Permit
21014-20000-03523
Plan Check / Job No.
B21VN09026
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT WITH 7'-6" X 17'-1" ADDITION (487 S.F ) PER GCS65852.2(e)(1)(A). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 5/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2021 APPLICANT
Assigned to Plan Check Engineer 7/17/2021 JEFFREY TANGONAN
Corrections Issued 7/17/2021 JEFFREY TANGONAN
Building Plans Picked Up 7/23/2021 APPLICANT
Issued 5/18/2023 APPLICANT
CofO in Progress 11/12/2024 OGANES TARAKHCHYAN
CofO Issued 11/15/2024 DANIEL ORRANTE
Permit Finaled 11/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/27/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/27/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/28/2021 CARLOS AGUILERA
Sewer availability Cleared 8/30/2021 CARLOS AGUILERA
Construction near power lines Cleared 10/4/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/13/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 3/20/2024 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 3/29/2024 Approved JOSE AVILA
Sewer 3/29/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Corrections Issued JOSE AVILA
Deputy Wood Construction 4/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/9/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/11/2024 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Rough 6/11/2024 Not Ready for Inspection JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Approved JOHN COLEMAN
ELECTRICAL-Rough 6/25/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/25/2024 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 6/25/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/8/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/8/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 7/8/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 7/8/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 7/8/2024 Approved OGANES TARAKHCHYAN
Pre-Inspection 7/22/2024 Partial Inspection JOSE AVILA
Insulation 7/24/2024 Approved OGANES TARAKHCHYAN
Shower Pan 8/2/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 8/7/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 8/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 8/13/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/13/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 9/4/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/25/2024 Approved GAREN HAYRAPETYAN
Final 10/25/2024 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 10/25/2024 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 10/25/2024 Approved GAREN HAYRAPETYAN
Service/Power Release 10/30/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Final 11/5/2024 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 11/5/2024 Approved OGANES TARAKHCHYAN