2355 S PROSSER AVE 90064

Certificate Information: 2355 S PROSSER AVE 90064

Application / Permit
21014-20000-03518
Plan Check / Job No.
B21VN09010
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20'-5" x 16'-5" (371 SQ. FT.) ADDITION TO AND CONVERT THE (E) 312 SQ. FT. DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g), RAISE THE (E) CEILING TO 9 FT. TO ALIGN WITH THE ADDITION PORTION. ALL WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 1/17/2022
Issuing Office
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 OMAR GARNICA
Corrections Issued 7/22/2021 OMAR GARNICA
Plan Check Approved 1/17/2022 OMAR GARNICA
Issued 1/17/2022 APPLICANT
Building Plans Picked Up 1/19/2022 APPLICANT
CofO in Progress 2/13/2023 STEPHANIE SWANSON
No Progress 2/13/2023 MICHAEL PELHAM
CofO in Progress 2/13/2023 MICHAEL PELHAM
No Progress 2/13/2023 MICHAEL PELHAM
CofO in Progress 2/13/2023 MICHAEL PELHAM
Permit Finaled 2/14/2023 DANIEL ORRANTE
CofO Issued 2/14/2023 DANIEL ORRANTE
Permit Finaled 2/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/27/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/28/2021 ANTHONY MAINEZ
Sewer availability Cleared 7/28/2021 ANTHONY MAINEZ
Specific Plan Cleared 11/16/2021 DANG NGUYEN
Specific Plan Cleared 11/18/2021 EDUARDO HERMOSO
Low Impact Development Cleared 12/22/2021 TA ANH
Roof/Waste drainage to street Cleared 12/29/2021 ANTHONY MAINEZ

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor La Expert Builders; Lic. No.: 1010734-B 9556 COZYCROFT AVE      CHATSWORTH, CA 91311

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/4/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 4/4/2022 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 4/12/2022 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 4/15/2022 Partial Approval BRENDAN LOONEY
METHANE-Subgrade 4/18/2022 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 4/19/2022 Partial Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 5/4/2022 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 5/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Barrier 5/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Subgrade 5/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/6/2022 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 5/16/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/9/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Corrections Issued BRENDAN LOONEY
Green Building Rough 6/9/2022 Not Ready for Inspection BRENDAN LOONEY
METHANE-Rough 6/9/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 7/14/2022 Corrections Issued JUAN VALENZUELA
HVAC-Rough 7/14/2022 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 7/14/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 7/20/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Rough 7/20/2022 Corrections Issued PATRICK QUALEY
Interior/Exterior Lathing 7/20/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Rough 7/20/2022 Not Ready for Inspection PATRICK QUALEY
Interior/Exterior Lathing 8/2/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 8/19/2022 Approved JOHN KIDWELL
HVAC-Rough 8/19/2022 Approved JOHN KIDWELL
PLUMBING-Rough 8/19/2022 Approved JOHN KIDWELL
Sewer 8/24/2022 Corrections Issued STEPHANIE SWANSON
Sewer 8/26/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 8/31/2022 Conditional Approval STEPHANIE SWANSON
Green Building Rough 8/31/2022 Corrections Issued STEPHANIE SWANSON
Insulation 8/31/2022 Conditional Approval STEPHANIE SWANSON
Interior/Exterior Lathing 8/31/2022 Partial Approval STEPHANIE SWANSON
METHANE-Barrier 8/31/2022 Approved STEPHANIE SWANSON
METHANE-Rough 8/31/2022 Approved STEPHANIE SWANSON
METHANE-Subgrade 8/31/2022 Approved STEPHANIE SWANSON
Sewer 9/14/2022 Approved STEPHANIE SWANSON
Drywall Nailing 9/19/2022 Not Ready for Inspection STEPHANIE SWANSON
Green Building Rough 9/19/2022 Approved STEPHANIE SWANSON
Drywall Nailing 9/21/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/7/2022 Approved STEPHANIE SWANSON
Shower Pan 10/7/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 1/20/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 1/20/2023 Corrections Issued STEPHANIE SWANSON
Final 1/20/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 1/20/2023 Approved STEPHANIE SWANSON
Green Building Final 1/20/2023 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Final 1/20/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 1/20/2023 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 1/20/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 2/3/2023 Approved STEPHANIE SWANSON
Final 2/3/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 2/3/2023 Approved STEPHANIE SWANSON
HVAC-Final 2/3/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 2/3/2023 Approved STEPHANIE SWANSON
Service/Power Release 2/3/2023 Approved STEPHANIE SWANSON
Final 2/10/2023 Conditional Approval STEPHANIE SWANSON
Service/Power Release 2/10/2023 Approved STEPHANIE SWANSON
Final 2/13/2023 OK to Issue CofO STEPHANIE SWANSON