14216 W WEIDNER ST 91331

Certificate Information: 14216 W WEIDNER ST 91331

Application / Permit
21014-20000-03513
Plan Check / Job No.
B21VN08990
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL. 25'-9" X 26'-2" ADDITION FOR TWO BEDROOMS AND TWO BATHROOMS TO (E) SINGLE FAMILY DWELLING. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION. FIRE SPRINKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 11/26/2021
Issuing Office
Current Status
CofO Issued on 7/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/16/2021 SERGIO MUNIZ
Corrections Issued 7/18/2021 SERGIO MUNIZ
Applicant returned to address corrections 10/25/2021 SERGIO MUNIZ
Applicant returned to address corrections 11/9/2021 SERGIO MUNIZ
Plan Check Approved 11/23/2021 SERGIO MUNIZ
Issued 11/26/2021 APPLICANT
Building Plans Picked Up 12/9/2021 APPLICANT
CofO in Progress 6/20/2023 JENNIFER RABUCHIN
Permit Finaled 7/31/2023 RUBEN SALAS
CofO Issued 7/31/2023 RUBEN SALAS
Permit Finaled 7/31/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/30/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/19/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 10/19/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/20/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/3/2022 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 1/3/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 1/3/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/14/2022 Partial Approval MARK JOHNSON
PLUMBING-Rough 1/14/2022 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/4/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/4/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 3/4/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 3/4/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/4/2022 Partial Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/18/2022 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 3/18/2022 Approved JENNIFER RABUCHIN
Green Building Rough 3/18/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/18/2022 Partial Approval JENNIFER RABUCHIN
Insulation 6/29/2022 Approved WILLIAM WREN
Drywall Nailing 7/8/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/8/2022 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 7/8/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/5/2022 Approved JENNIFER RABUCHIN
Final 12/5/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/5/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 12/5/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/5/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 12/5/2022 Approved JENNIFER RABUCHIN
Final 5/9/2023 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 5/9/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/16/2023 Approved JENNIFER RABUCHIN
Final 6/16/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 6/16/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/16/2023 Approved JENNIFER RABUCHIN