14216 W WEIDNER ST 91331
Certificate Information: 14216 W WEIDNER ST 91331
- Application / Permit
- 21014-20000-03513
- Plan Check / Job No.
- B21VN08990
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL. 25'-9" X 26'-2" ADDITION FOR TWO BEDROOMS AND TWO BATHROOMS TO (E) SINGLE FAMILY DWELLING. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION. FIRE SPRINKLER REQUIRED NFPA-13D.
- Permit Issued
- Issued on 11/26/2021
- Issuing Office
- Current Status
- CofO Issued on 7/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2021 | SERGIO MUNIZ |
| Corrections Issued | 7/18/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/25/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 11/9/2021 | SERGIO MUNIZ |
| Plan Check Approved | 11/23/2021 | SERGIO MUNIZ |
| Issued | 11/26/2021 | APPLICANT |
| Building Plans Picked Up | 12/9/2021 | APPLICANT |
| CofO in Progress | 6/20/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 7/31/2023 | RUBEN SALAS |
| CofO Issued | 7/31/2023 | RUBEN SALAS |
| Permit Finaled | 7/31/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 10/19/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/19/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/20/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/14/2022 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 1/14/2022 | Partial Approval | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 3/4/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 3/4/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/4/2022 | Partial Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/18/2022 | Partial Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/18/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 6/29/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 7/8/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/8/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/8/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | JENNIFER RABUCHIN |
| Final | 12/5/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/5/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/5/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 12/5/2022 | Approved | JENNIFER RABUCHIN |
| Final | 5/9/2023 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/9/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/16/2023 | Approved | JENNIFER RABUCHIN |
| Final | 6/16/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 6/16/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/16/2023 | Approved | JENNIFER RABUCHIN |