20342-20344 W LORNE ST 91306
Certificate Information: 20342-20344 W LORNE ST 91306
- Application / Permit
- 21014-20000-03511
- Plan Check / Job No.
- B21VN08987
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF THE SINGLE FAMILY DWELLING TO AN ACCESSORY DWELLING UNIT WITH 1ST AND 2ND STORY ADDITION PER LAMC 12.22A33(c)AND(d), AND 2ND FLOOR ADDITION TO THE (E) SFD ABOVE THE (E) CARPORT.
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- CofO Issued on 3/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | COLIN LOREDO |
| Corrections Issued | 8/26/2021 | COLIN LOREDO |
| Quality Review Completed | 9/7/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/7/2021 | APPLICANT |
| Plan Check Approved | 12/21/2021 | COLIN LOREDO |
| Issued | 12/22/2021 | APPLICANT |
| CofO in Progress | 1/25/2023 | ALEXANDER HANDY |
| Permit Finaled | 3/14/2023 | JOHN JANSON |
| CofO Issued | 3/14/2023 | JOHN JANSON |
| Permit Finaled | 3/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/9/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 11/30/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 12/1/2021 | LEE GUILBEAUX |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/9/2022 | Partial Approval | STEVEN BACK |
| Sewer | 2/9/2022 | Approved | STEVEN BACK |
| Deputy Drilled-In Anchors | 3/17/2022 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 3/21/2022 | Corrections Issued | STEVEN BACK |
| Deputy Drilled-In Anchors | 4/5/2022 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 4/8/2022 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 7/1/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 7/1/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 8/1/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | PETER FOLLING |
| Green Building Rough | 8/1/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 8/1/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 8/1/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 8/5/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 8/5/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 8/19/2022 | Partial Approval | KRISTEN CAUSEY |
| Green Building Rough | 8/19/2022 | Approved | KRISTEN CAUSEY |
| Insulation | 8/19/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 8/23/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 8/23/2022 | Approved | STEVEN BACK |
| Insulation | 8/23/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/23/2022 | Partial Approval | STEVEN BACK |
| Interior/Exterior Lathing | 9/21/2022 | Approved | STEVEN BACK |
| Shower Pan | 9/21/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 1/24/2023 | Approved | ALEXANDER HANDY |
| Final | 1/24/2023 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 1/24/2023 | Approved | ALEXANDER HANDY |
| HVAC-Final | 1/24/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/24/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 1/24/2023 | Approved | ALEXANDER HANDY |