5756 N CANTALOUPE AVE 91401

Certificate Information: 5756 N CANTALOUPE AVE 91401

Application / Permit
21014-20000-03500
Plan Check / Job No.
B21VN08973
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST & 2ND FLOOR ADDITION & REMODEL TO (E) SINGLE FAMILY DWELLING, NEW WINDOWS, NEW DOORS AND REROOF. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/10/2022
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 COLIN LOREDO
Corrections Issued 8/16/2021 COLIN LOREDO
Quality Review Completed 8/27/2021 OMID HEDAYAT
Building Plans Picked Up 9/3/2021 APPLICANT
Plan Check Approved 2/3/2022 COLIN LOREDO
No Progress 4/11/2022 COLIN LOREDO
Issued 5/10/2022 APPLICANT
CofO in Progress 5/8/2023 RYAN SALAZAR
Permit Finaled 5/11/2023 MICHAEL SMITH
CofO Issued 5/11/2023 MICHAEL SMITH
Permit Finaled 5/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/3/2021 CARLOS AGUILERA
Sewer availability Cleared 11/3/2021 CARLOS AGUILERA
Low Impact Development Cleared 1/13/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 1/24/2022 JOSE DUARTE-DIAZ

Contact Information

Architect Lepair,, Yoram A; Lic. No.: C36127 850 S ROBERTSON BLVD      LOS ANGELES, CA 90035
Contractor Kasteler Construction Inc; Lic. No.: 1039992-B 4958 MARMOL DR      WOODLAND HILLS, CA 91364

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/15/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 6/17/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 7/6/2022 Corrections Issued DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 7/11/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 7/11/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 8/16/2022 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/25/2022 Corrections Issued ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 9/16/2022 Not Ready for Inspection RICHARD DOCKUS
Insulation 9/22/2022 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 9/26/2022 Approved RICHARD DOCKUS
HVAC-Rough 9/26/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 9/28/2022 Approved RICHARD DOCKUS
Green Building Rough 9/28/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 9/28/2022 Approved RICHARD DOCKUS
Insulation 9/30/2022 Corrections Issued DEANDRE HOFFMAN
Interior/Exterior Lathing 9/30/2022 Partial Approval DEANDRE HOFFMAN
Insulation 10/4/2022 Approved ROBERT GOLD
Interior/Exterior Lathing 10/4/2022 Partial Approval ROBERT GOLD
Deputy Wood Construction 10/7/2022 Conditional Approval RICHARD DOCKUS
Drywall Nailing 10/11/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 10/11/2022 Approved RICHARD DOCKUS
Shower Pan 10/11/2022 Approved RICHARD DOCKUS
Underground Mechanical 2/1/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 3/6/2023 Corrections Issued RYAN SALAZAR
Final 3/6/2023 Corrections Issued RYAN SALAZAR
HVAC-Final 3/6/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Final 3/15/2023 Approved RYAN SALAZAR
Final 5/3/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/3/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/3/2023 Approved RYAN SALAZAR