12950 W HAYNES ST 91606
Certificate Information: 12950 W HAYNES ST 91606
- Application / Permit
- 21014-20000-03492
- Plan Check / Job No.
- B21VN08952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 8' X 20' 2" PORCH ADDITION TO FRONT, 11' 10" X 17' 5" PATIO COVER AND 4' X 17' 5" HABITABLE SPACE ADDITION TO REAR AND INTERIOR REMODEL TO (E) SFD TO ADD (1) BEDROOM/BATHROOM/CLOSET, REMODEL KITCHEN, RELOCATE (1) BATHROOM & REVISE ENTRANCE OF GARAGE/DRIVEWAY/CURB CUT. ALL WORK DONE PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 05/18/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 10/20/2021
- Issuing Office
- Current Status
- CofO Issued on 12/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 8/24/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/20/2021 | GURUNATH NESARAJAH |
| Issued | 10/20/2021 | APPLICANT |
| Building Plans Picked Up | 10/21/2021 | APPLICANT |
| CofO in Progress | 10/5/2022 | BRYAN MEYER |
| CofO in Progress | 10/17/2022 | BRYAN MEYER |
| Permit Finaled | 12/6/2022 | DAVID JAMES |
| CofO Issued | 12/6/2022 | DAVID JAMES |
| Permit Finaled | 12/6/2022 | DAVID JAMES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 7/20/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/21/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/8/2021 | Not Ready for Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 11/8/2021 | Not Ready for Inspection | BRYAN MEYER |
| Excavation/Setback/Form/Re-Bar | 11/16/2021 | Corrections Issued | BRYAN MEYER |
| Footing/Foundation/Slab | 11/16/2021 | Partial Inspection | BRYAN MEYER |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Approved | BRYAN MEYER |
| BUILDING-Rough-Frame | 12/7/2021 | Partial Inspection | BRYAN MEYER |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Partial Approval | BRYAN MEYER |
| BUILDING-Rough-Frame | 2/22/2022 | Not Ready for Inspection | BRYAN MEYER |
| ELECTRICAL-Rough | 2/22/2022 | Partial Inspection | BRYAN MEYER |
| Green Building Rough | 2/22/2022 | Partial Inspection | BRYAN MEYER |
| HVAC-Rough | 2/22/2022 | Partial Inspection | BRYAN MEYER |
| PLUMBING-Rough | 2/22/2022 | Not Ready for Inspection | BRYAN MEYER |
| Rough-Elec/Plmb/HVAC | 2/22/2022 | Partial Inspection | BRYAN MEYER |
| BUILDING-Rough-Frame | 3/23/2022 | Partial Approval | BRYAN MEYER |
| ELECTRICAL-Rough | 3/23/2022 | Partial Inspection | BRYAN MEYER |
| Green Building Rough | 3/23/2022 | Partial Inspection | BRYAN MEYER |
| HVAC-Rough | 3/23/2022 | Partial Approval | BRYAN MEYER |
| PLUMBING-Rough | 3/23/2022 | Corrections Issued | BRYAN MEYER |
| BUILDING-Rough-Frame | 3/25/2022 | Partial Approval | BRYAN MEYER |
| ELECTRICAL-Rough | 3/25/2022 | Approved | BRYAN MEYER |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Approved | BRYAN MEYER |
| Green Building Rough | 3/25/2022 | Not Ready for Inspection | BRYAN MEYER |
| HVAC-Rough | 3/25/2022 | Approved | BRYAN MEYER |
| PLUMBING-Rough | 3/25/2022 | Not Ready for Inspection | BRYAN MEYER |
| Rough-Elec/Plmb/HVAC | 3/25/2022 | Approved | BRYAN MEYER |
| ELECTRICAL-Rough | 4/5/2022 | Approved | BRYAN MEYER |
| HVAC-Rough | 4/5/2022 | Approved | BRYAN MEYER |
| Insulation | 4/5/2022 | Approved | BRYAN MEYER |
| PLUMBING-Rough | 4/5/2022 | Approved | BRYAN MEYER |
| Drywall Nailing | 5/19/2022 | Approved | KIM BEAUCHAMP |
| Interior/Exterior Lathing | 6/21/2022 | Approved | BRYAN MEYER |
| BUILDING-Rough-Frame | 9/27/2022 | Approved | BRYAN MEYER |
| ELECTRICAL-Final | 9/27/2022 | Partial Inspection | BRYAN MEYER |
| Final | 9/27/2022 | Partial Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 9/27/2022 | Approved | BRYAN MEYER |
| Green Building Final | 9/27/2022 | Approved | BRYAN MEYER |
| Green Building Rough | 9/27/2022 | Approved | BRYAN MEYER |
| HVAC-Final | 9/27/2022 | Partial Inspection | BRYAN MEYER |
| PLUMBING-Final | 9/27/2022 | Partial Inspection | BRYAN MEYER |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | BRYAN MEYER |
| Service/Power Release | 9/27/2022 | Approved | BRYAN MEYER |
| Smoke Detectors | 9/27/2022 | Approved | BRYAN MEYER |
| ELECTRICAL-Final | 10/3/2022 | Approved | BRYAN MEYER |
| Final | 10/3/2022 | Conditional Approval | BRYAN MEYER |
| HVAC-Final | 10/3/2022 | Approved | BRYAN MEYER |
| PLUMBING-Final | 10/3/2022 | Approved | BRYAN MEYER |
| Final | 10/17/2022 | OK to Issue CofO | BRYAN MEYER |