6249-6251 N LEMONA AVE 91411

Certificate Information: 6249-6251 N LEMONA AVE 91411

Application / Permit
21014-20000-03491
Plan Check / Job No.
B21VN08946
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
(E) GARAGE TO BE CONVERTED TO (N) J.A.D.U AND SFD REMODEL.
Permit Issued
Issued on 9/7/2022
Issuing Office
Current Status
Issued on 9/7/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/14/2021 JOE VO
Corrections Issued 7/14/2021 JOE VO
Applicant returned to address corrections 11/5/2021 JOE VO
Plan Check Approved 7/13/2022 JOE VO
Issued 9/7/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/20/2021 CARLOS AGUILERA
Sewer availability Cleared 7/20/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/21/2021 CARLOS AGUILERA
Construction near power lines Cleared 11/2/2021 RIDWAN HARDY
Miscellaneous Cleared 8/24/2022 JOE VO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/11/2022 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 10/12/2022 Conditional Approval MICHAEL SMITH
Deputy Drilled-In Anchors 10/18/2022 Partial Approval ROBERT GOLD
PLUMBING-Rough 10/27/2022 Corrections Issued RICHARD DOCKUS
Piling/Pier/Caisson 10/27/2022 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 11/4/2022 Approved RICHARD DOCKUS
Footing/Foundation/Slab 11/4/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 11/4/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 11/18/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 11/18/2022 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 11/18/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 11/18/2022 Not Ready for Inspection JACK KARGODORIAN
METHANE-Rough 11/18/2022 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 11/18/2022 Not Ready for Inspection JACK KARGODORIAN
Sewer 11/18/2022 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 11/18/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 3/28/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 3/28/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 3/28/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/6/2023 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 4/6/2023 Approved RYAN SALAZAR
HVAC-Rough 4/6/2023 Approved RYAN SALAZAR
Insulation 4/6/2023 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 4/19/2023 Partial Approval RYAN SALAZAR
Drywall Nailing 4/19/2023 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 4/19/2023 Approved RYAN SALAZAR
Drywall Nailing 4/25/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/25/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 8/22/2023 Approved RYAN SALAZAR
Final 8/22/2023 Corrections Issued RYAN SALAZAR
Green Building Final 8/22/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 8/22/2023 Approved RYAN SALAZAR
METHANE-Final 8/22/2023 Approved RYAN SALAZAR
METHANE-Rough 8/22/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 8/22/2023 Approved RYAN SALAZAR
Final 8/30/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Final 8/30/2023 Not Ready for Inspection RYAN SALAZAR