17556 W DEVONSHIRE ST 91325

Certificate Information: 17556 W DEVONSHIRE ST 91325

Application / Permit
21014-20000-03490
Plan Check / Job No.
B21VN08943
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 32'-1" X 14'-10" DEN AND MASTER BEDROOM/BATHROOM TO SIDE OF (E) SFD. ALL WORK DONE PER ENGR DESIGN.
Permit Issued
Issued on 12/16/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 7/19/2022 GURUNATH NESARAJAH
Corrections Issued 7/19/2022 GURUNATH NESARAJAH
Building Plans Picked Up 7/20/2022 APPLICANT
Applicant returned to address corrections 11/18/2022 HAYATO TSUCHIYA
Plan Check Approved 12/13/2022 DANIEL ABRAMYAN
Issued 12/16/2022 APPLICANT
CofO in Progress 8/27/2024 JAVIER RAMOS JR
Permit Finaled 11/18/2024 DANIEL ORRANTE
CofO Issued 11/18/2024 DANIEL ORRANTE
Permit Finaled 11/18/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/20/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 7/20/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 7/21/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 7/21/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 7/21/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 7/21/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/14/2023 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/18/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 4/21/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 11/9/2023 Approved JAVIER RAMOS JR
Wood Frame 11/9/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 11/17/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/17/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/17/2023 Approved JAVIER RAMOS JR
Insulation 11/22/2023 Corrections Issued ROBERT GOLD
Interior/Exterior Lathing 11/22/2023 Partial Approval ROBERT GOLD
HVAC-Rough 11/29/2023 Approved JAVIER RAMOS JR
Insulation 11/29/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/29/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/13/2023 Approved JAVIER RAMOS JR
Drywall Nailing 12/13/2023 Approved JAVIER RAMOS JR
Green Building Rough 12/13/2023 Approved JAVIER RAMOS JR
Shower Pan 12/22/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 12/26/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Final 6/21/2024 Approved JAVIER RAMOS JR
Final 6/21/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/21/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/21/2024 Approved JAVIER RAMOS JR
Final 8/23/2024 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 8/23/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 8/23/2024 Approved JAVIER RAMOS JR