22056-22058 W LOPEZ ST 91364
Certificate Information: 22056-22058 W LOPEZ ST 91364
- Application / Permit
- 21014-20000-03479
- Plan Check / Job No.
- B21VN08910
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan ADU addiiton. 1ST AND 2ND STORY ADDITION AND CONVERSION OF THE EXISTING ATTACHED GARAGE TO CREATE A NEW A.D.U. ADDITION OF A NEW CARPORT AND COVERED PORCH. ALL WORK PER ENGINEERING DESIGN. "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certification of Occupancy."
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Valley
- Current Status
- Issued on 2/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 8/23/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 8/26/2021 | WING SUEN |
| Applicant returned to address corrections | 1/11/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 1/28/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 2/2/2022 | CRYSTEL MAALOUF |
| Issued | 2/15/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/24/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 11/24/2021 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 11/29/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 2/2/2022 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 2/2/2022 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/23/2022 | Conditional Approval | JESUS PINEDA |
| PLUMBING-Rough | 2/24/2022 | Partial Approval | PETER FOLLING |
| Sewer | 2/24/2022 | Approved | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 3/15/2022 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 3/15/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | PETER FOLLING |
| Wood Frame | 5/12/2022 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Approved | PETER FOLLING |
| Wood Frame | 7/21/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 2/17/2023 | Approved | SEAN WIRCH |
| Green Building Rough | 2/17/2023 | Approved | SEAN WIRCH |
| HVAC-Rough | 2/17/2023 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 2/17/2023 | Approved | SEAN WIRCH |
| Service/Power Release | 2/17/2023 | Not Ready for Inspection | SEAN WIRCH |
| Insulation | 11/22/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 11/22/2023 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 7/22/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/30/2024 | Partial Approval | JOHN COLEMAN |