15650 W SIMONDS ST 91344
Certificate Information: 15650 W SIMONDS ST 91344
- Application / Permit
- 21014-20000-03420
- Plan Check / Job No.
- B21VN08781
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & REMODEL TO (E) SFD
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- Issued on 11/16/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2021 | JESSE ARELLANO |
| Corrections Issued | 7/13/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 9/2/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 11/1/2021 | JESSE ARELLANO |
| Issued | 11/16/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/14/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2021 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 11/1/2021 | JESSE ARELLANO |
| Roof/Waste drainage to street | Cleared | 11/2/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 1/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/25/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/18/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/18/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 5/2/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/6/2022 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 5/18/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| Final | 9/23/2022 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Final | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 9/23/2022 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 1/17/2023 | Approved | JENNIFER RABUCHIN |
| Final | 1/17/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 1/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 1/17/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 1/17/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 1/17/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/17/2023 | Approved | JENNIFER RABUCHIN |