2633 S BARRY AVE 90064
Certificate Information: 2633 S BARRY AVE 90064
- Application / Permit
- 21014-20000-03412
- Plan Check / Job No.
- B21VN08745
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 45'-2" X 33'-3" IRREGULAR SHAPED ADDITION AND INTERIOR REMODEL TO SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- CofO Issued on 11/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 7/24/2021 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 8/26/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 11/22/2021 | ARTIN ZARUKIAN |
| Issued | 11/22/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| CofO in Progress | 10/31/2022 | JOHNNY MIRANDA |
| Permit Finaled | 11/1/2022 | DANIEL ORRANTE |
| CofO Issued | 11/1/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/1/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/1/2021 | PETE EYRE |
| Low Impact Development | Cleared | 11/2/2021 | SAHIL SHARMA |
| Roof/Waste drainage to street | Cleared | 11/12/2021 | TRACY TATE |
| Sewer availability | Cleared | 11/18/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2021 | TRACY TATE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tabirara,, Vernon Nicolas; Lic. No.: C75492 | 17520 DAPHNE AVE TORRANCE, CA 90504 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/3/2021 | Corrections Issued | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 1/13/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/13/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2022 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 1/26/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Partial Approval | PATRICK QUALEY |
| HVAC-Rough | 5/11/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/13/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/13/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/13/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 5/13/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/18/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 5/18/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 5/18/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/18/2022 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 5/18/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 5/23/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 5/23/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 6/1/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/29/2022 | Approved | JOHNNY MIRANDA |
| Final | 8/29/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 8/29/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 8/29/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 8/29/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 8/29/2022 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 8/29/2022 | Approved | JOHNNY MIRANDA |
| Final | 10/27/2022 | OK to Issue CofO | JOHNNY MIRANDA |