17031 W OSBORNE ST 91325
Certificate Information: 17031 W OSBORNE ST 91325
- Application / Permit
- 21014-20000-03401
- Plan Check / Job No.
- B21VN08707
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 29'-9" X 20' ONE-STORY ADDITION TO EXISITING SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofO Issued on 4/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | OMAR GARNICA |
| Corrections Issued | 7/7/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 7/20/2021 | OMAR GARNICA |
| Plan Check Approved | 10/6/2021 | OMAR GARNICA |
| Building Plans Picked Up | 10/7/2021 | APPLICANT |
| Issued | 10/19/2021 | APPLICANT |
| CofO in Progress | 2/15/2024 | JAVIER RAMOS JR |
| Permit Finaled | 4/15/2024 | DANIEL ORRANTE |
| CofO Issued | 4/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/9/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/9/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 9/30/2021 | SUNG JOON WON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 6541 ODESSA AVE UNIT 11 LAKE BALBOA, CA 91406 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/21/2022 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 4/5/2022 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 4/7/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/19/2022 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/19/2022 | Conditional Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/19/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 7/19/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 7/19/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/19/2022 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 8/4/2022 | Conditional Approval | JAVIER RAMOS JR |
| Insulation | 8/4/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 8/4/2022 | Partial Approval | ALAN MORELOS |
| BUILDING-Rough-Frame | 8/17/2022 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 8/17/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/17/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 8/17/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/14/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/14/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/17/2023 | Approved | JAVIER RAMOS JR |
| Final | 2/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/17/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/17/2023 | Approved | JAVIER RAMOS JR |
| Final | 2/15/2024 | OK to Issue CofO | JAVIER RAMOS JR |