17031 W OSBORNE ST 91325

Certificate Information: 17031 W OSBORNE ST 91325

Application / Permit
21014-20000-03401
Plan Check / Job No.
B21VN08707
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 29'-9" X 20' ONE-STORY ADDITION TO EXISITING SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2021 APPLICANT
Assigned to Plan Check Engineer 7/7/2021 OMAR GARNICA
Corrections Issued 7/7/2021 OMAR GARNICA
Applicant returned to address corrections 7/20/2021 OMAR GARNICA
Plan Check Approved 10/6/2021 OMAR GARNICA
Building Plans Picked Up 10/7/2021 APPLICANT
Issued 10/19/2021 APPLICANT
CofO in Progress 2/15/2024 JAVIER RAMOS JR
Permit Finaled 4/15/2024 DANIEL ORRANTE
CofO Issued 4/15/2024 DANIEL ORRANTE
Permit Finaled 4/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/9/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/9/2021 CARLOS AGUILERA
Sewer availability Cleared 7/9/2021 CARLOS AGUILERA
Low Impact Development Cleared 9/30/2021 SUNG JOON WON

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 6541 ODESSA AVE UNIT 11      LAKE BALBOA, CA 91406

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/21/2022 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/5/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 4/7/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/19/2022 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 7/19/2022 Conditional Approval JAVIER RAMOS JR
ELECTRICAL-Rough 7/19/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 7/19/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 7/19/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 7/19/2022 Approved JAVIER RAMOS JR
Deputy Wood Construction 8/4/2022 Conditional Approval JAVIER RAMOS JR
Insulation 8/4/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 8/4/2022 Partial Approval ALAN MORELOS
BUILDING-Rough-Frame 8/17/2022 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 8/17/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 8/17/2022 Approved JAVIER RAMOS JR
Green Building Rough 8/17/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/14/2022 Approved JAVIER RAMOS JR
Shower Pan 9/14/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/17/2023 Approved JAVIER RAMOS JR
Final 2/17/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 2/17/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 2/17/2023 Approved JAVIER RAMOS JR
Final 2/15/2024 OK to Issue CofO JAVIER RAMOS JR