13224 W BEAVER ST 91342
Certificate Information: 13224 W BEAVER ST 91342
- Application / Permit
- 21014-20000-03386
- Plan Check / Job No.
- B21VN08674
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'6" X 26' ADDITION TO (E) ADU
- Permit Issued
- Issued on 12/17/2021
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | HERNAN ARREOLA |
| Corrections Issued | 7/8/2021 | HERNAN ARREOLA |
| Plan Check Approved | 12/14/2021 | HERNAN ARREOLA |
| Issued | 12/17/2021 | APPLICANT |
| CofO in Progress | 8/18/2025 | KEVIN BERBERYAN |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
| CofO Issued | 9/4/2025 | RUBEN SALAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/12/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/17/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2022 | Corrections Issued | JOHN HAYES |
| Pre-Inspection | 6/23/2022 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 6/28/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/18/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/18/2022 | Corrections Issued | ARAM AVEDISIAN |
| Insulation | 7/25/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/23/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/23/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/1/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/1/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/1/2022 | Conditional Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/1/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 9/15/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/15/2022 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 9/27/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/27/2022 | Approved | ARAM AVEDISIAN |
| Shower Pan | 9/27/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/10/2022 | Partial Approval | ARAM AVEDISIAN |
| Final | 2/2/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 2/2/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 2/2/2023 | Approved | ARAM AVEDISIAN |
| Final | 8/18/2025 | OK to Issue CofO | KEVIN BERBERYAN |