23017-23019 W GILMORE ST 91307

Certificate Information: 23017-23019 W GILMORE ST 91307

Application / Permit
21014-20000-03372
Plan Check / Job No.
B21VN08584
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO ATTACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2021 APPLICANT
Assigned to Plan Check Engineer 7/6/2021 CARLOS MONTES
Corrections Issued 7/6/2021 CARLOS MONTES
Plan Check Approved 7/8/2021 CARLOS MONTES
Issued 7/14/2021 APPLICANT
CofO in Progress 12/29/2021 TROY SANDERS
CofO Issued 2/17/2022 JOHN JANSON
Permit Finaled 2/17/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/7/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/7/2021 CARLOS AGUILERA
Sewer availability Cleared 7/7/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Levin,, Vladimir; Lic. No.: C35001 11606 CHENAULT STR, UNIT 301      LOS ANGELES, CA 90049

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/7/2021 Partial Approval PETER FOLLING
Footing/Foundation/Slab 9/14/2021 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 9/17/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 10/7/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 10/7/2021 Approved TROY SANDERS
Insulation 10/7/2021 Partial Approval TROY SANDERS
PLUMBING-Rough 10/7/2021 Approved TROY SANDERS
Insulation 10/13/2021 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 10/18/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 10/22/2021 Approved TROY SANDERS
Drywall Nailing 10/22/2021 Partial Approval TROY SANDERS
Green Building Rough 10/22/2021 Approved TROY SANDERS
Insulation 10/22/2021 Approved TROY SANDERS
Interior/Exterior Lathing 10/22/2021 Approved TROY SANDERS
Drywall Nailing 10/25/2021 Approved JESUS PINEDA
Final 12/22/2021 Corrections Issued TROY SANDERS
Green Building Final 12/22/2021 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 12/22/2021 Approved TROY SANDERS
Final 12/29/2021 OK to Issue CofO TROY SANDERS