6235 N ELLENVIEW AVE 91307

Certificate Information: 6235 N ELLENVIEW AVE 91307

Application / Permit
21014-20000-03357
Plan Check / Job No.
B21VN08543
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(18'-7 1/2"x 26'-9") 498 SQFT ADDITION OF TWO BATHS AND TWO CLOSETS ABOVE (E) ATTACHED GARAGE
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 PETER MOSESIAN
Corrections Issued 8/8/2021 PETER MOSESIAN
Quality Review Completed 8/20/2021 OMID HEDAYAT
Building Plans Picked Up 8/26/2021 APPLICANT
Plan Check Approved 9/28/2021 PETER MOSESIAN
Issued 9/28/2021 APPLICANT
CofO in Progress 8/16/2022 TROY SANDERS
CofO Issued 9/10/2022 DANIEL ORRANTE
Permit Finaled 9/10/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/31/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/1/2021 DAGOVERTO GUERRERO
ZA Case Cleared 9/14/2021 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Mario Alberto; Lic. No.: C89006 43023 40TH ST WEST      LANCASTER, CA 93536

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/7/2021 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 10/7/2021 Approved TROY SANDERS
Footing/Foundation/Slab 10/7/2021 Approved TROY SANDERS
Deputy Drilled-In Anchors 10/13/2021 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 10/14/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval JESUS PINEDA
Green Building Rough 10/29/2021 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 11/22/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval TROY SANDERS
PLUMBING-Rough 11/22/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Approved TROY SANDERS
Interior/Exterior Lathing 12/8/2021 No Access for Inspection TROY SANDERS
BUILDING-Rough-Frame 12/29/2021 Approved TROY SANDERS
Green Building Rough 12/29/2021 Approved TROY SANDERS
Interior/Exterior Lathing 12/29/2021 Partial Approval TROY SANDERS
Insulation 1/11/2022 No Access for Inspection JUSTIN HAWLEY
Drywall Nailing 1/24/2022 Partial Approval JUSTIN HAWLEY
Interior/Exterior Lathing 1/24/2022 Partial Inspection JUSTIN HAWLEY
Drywall Nailing 3/2/2022 Approved JESUS PINEDA
Shower Pan 3/2/2022 Approved JESUS PINEDA
Final 8/15/2022 OK to Issue CofO TROY SANDERS
Green Building Final 8/15/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/15/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 8/15/2022 Approved TROY SANDERS