14561 W HUSTON ST 91403

Certificate Information: 14561 W HUSTON ST 91403

Application / Permit
21014-20000-03356
Plan Check / Job No.
B21VN08540
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
830 SQ. FT. ADDITION & MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/14/2022
Issuing Office
Current Status
CofO Issued on 5/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 COLIN LOREDO
Corrections Issued 8/12/2021 COLIN LOREDO
Quality Review Completed 8/20/2021 OMID HEDAYAT
Building Plans Picked Up 8/25/2021 APPLICANT
Applicant returned to address corrections 10/14/2021 COLIN LOREDO
Plan Check Approved 1/25/2022 COLIN LOREDO
Issued 6/14/2022 APPLICANT
CofO in Progress 4/23/2025 JACK KARGODORIAN
Permit Finaled 5/1/2025 RUBEN SALAS
CofO Issued 5/1/2025 RUBEN SALAS
Permit Finaled 5/1/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 8/27/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/8/2021 GABRIEL ROBLES
ZI Cleared 9/24/2021 KENTON TRINH
Low Impact Development Cleared 1/11/2022 TA ANH
Roof/Waste drainage to street Cleared 1/11/2022 ABDULLAH SADOZAI

Contact Information

Contractor Express Remodeling And Plumbing; Lic. No.: 919808-B P O BOX 4371      BURBANK, CA 91503
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/20/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 7/28/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2022 Corrections Issued JOHN HAYES
PLUMBING-Rough 1/26/2023 Approved THOMAS FINNILA
Wood Frame 1/26/2023 Not Ready for Inspection THOMAS FINNILA
Deputy Wood Construction 1/27/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 2/28/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 2/28/2023 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 2/28/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 2/28/2023 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 2/28/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 4/14/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 4/14/2023 Not Ready for Inspection THOMAS FINNILA
Wood Frame 4/14/2023 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 4/21/2023 Approved THOMAS FINNILA
Wood Frame 4/21/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 5/24/2023 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Approved THOMAS FINNILA
Green Building Rough 5/24/2023 Approved THOMAS FINNILA
HVAC-Rough 5/24/2023 Approved THOMAS FINNILA
MERV13>=Rough 5/24/2023 Approved THOMAS FINNILA
Insulation 6/27/2023 Corrections Issued THOMAS FINNILA
Insulation 6/30/2023 Approved THOMAS FINNILA
Drywall Nailing 7/3/2023 Partial Approval THOMAS FINNILA
Drywall Nailing 7/10/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/23/2023 Partial Approval RYAN SALAZAR
Shower Pan 8/23/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/31/2023 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Final 1/2/2024 Not Ready for Inspection THOMAS FINNILA
Final 1/2/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 1/2/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 1/2/2024 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Approved THOMAS FINNILA
ELECTRICAL-Final 2/7/2024 Corrections Issued CRAIG DAVIS
Final 2/7/2024 Not Ready for Inspection CRAIG DAVIS
Green Building Final 2/7/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 2/7/2024 Corrections Issued CRAIG DAVIS
MERV13>=Final 2/7/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 2/7/2024 Corrections Issued CRAIG DAVIS
Smoke Detectors 2/7/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 2/14/2024 Approved MISAEL ESPARZA
Final 2/14/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 2/14/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 2/14/2024 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Final 2/14/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 2/14/2024 Approved MISAEL ESPARZA
Final 3/11/2024 Partial Approval JOHN COLEMAN
Green Building Final 3/11/2024 Approved JOHN COLEMAN
HVAC-Final 3/11/2024 Approved JOHN COLEMAN
MERV13>=Final 3/11/2024 Approved JOHN COLEMAN
PLUMBING-Final 3/11/2024 Approved JOHN COLEMAN
Final 4/22/2025 OK to Issue CofO JACK KARGODORIAN