12349 N TELFAIR AVE 91342

Certificate Information: 12349 N TELFAIR AVE 91342

Application / Permit
21014-20000-03351
Plan Check / Job No.
B21VN08517
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE 11'X 19' PORTION OF THE (E) PATIO OVER AND ADD A NEW 16' X 31' ADDITION OF TWO BEDROOMS, TWO BATHROOMS AND A LAUNDRY ROOM TO (E) SINGLE FAMILY DWELLING PER WFPP.
Permit Issued
Issued on 1/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2021 APPLICANT
Assigned to Plan Check Engineer 7/9/2021 SERGIO MUNIZ
Corrections Issued 7/10/2021 SERGIO MUNIZ
Applicant returned to address corrections 12/10/2021 SERGIO MUNIZ
Plan Check Approved 12/29/2021 SERGIO MUNIZ
Building Plans Picked Up 12/29/2021 APPLICANT
Issued 1/26/2022 APPLICANT
CofO in Progress 10/13/2025 JENNIFER RABUCHIN
Permit Finaled 2/14/2026 MICHAEL PELHAM
Permit Finaled 2/14/2026 MICHAEL PELHAM
CofO Issued 2/14/2026 MICHAEL PELHAM

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/23/2021 TIMOTHY POWELL
Low Impact Development Cleared 12/2/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 12/6/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/7/2021 CARLOS AGUILERA
Sewer availability Cleared 12/7/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/1/2022 Partial Approval CHRISTOPHER DELLEFIELD
Pre-Inspection 8/1/2022 Approved CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 8/5/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/24/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/24/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/31/2022 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 8/31/2022 Approved JENNIFER RABUCHIN
Green Building Rough 8/31/2022 Approved JENNIFER RABUCHIN
Insulation 8/31/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/31/2022 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 9/8/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/26/2022 Approved JENNIFER RABUCHIN
Final 9/26/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 9/26/2022 Approved JENNIFER RABUCHIN
Green Building Final 9/26/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 9/26/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/10/2025 Approved JENNIFER RABUCHIN
Final 10/10/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 10/10/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/10/2025 Approved JENNIFER RABUCHIN