20807-20809 W BURBANK BLVD 91367
Certificate Information: 20807-20809 W BURBANK BLVD 91367
- Application / Permit
- 21014-20000-03344
- Plan Check / Job No.
- B21VN08492
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- 16'-5" X 23'-10" ADDITION OF A FAMILY ROOM AND BATHROOM TO THE (E) SFD, AND CONVERT THE (E) 20'-0" X 20'-7" ATTACHED GARAGE INTO A (N) JR. ACCESSORY DWELLING UNIT PER 65852.2 (e)(1)(A) AND 65852.22. ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- CofO Issued on 2/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | PARISA ZAHABI |
| Corrections Issued | 7/22/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 8/11/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 8/23/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 9/4/2021 | PARISA ZAHABI |
| Issued | 9/13/2021 | APPLICANT |
| Building Plans Picked Up | 9/15/2021 | APPLICANT |
| CofO in Progress | 2/17/2022 | STEVEN BACK |
| Permit Finaled | 2/18/2022 | JOHN JANSON |
| CofO Issued | 2/18/2022 | JOHN JANSON |
| Permit Finaled | 2/18/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/27/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/27/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 9/8/2021 | TIMOTHY POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/22/2021 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 9/22/2021 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 9/24/2021 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 9/27/2021 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 9/27/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2021 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 10/20/2021 | Corrections Issued | DAVID SANDOVAL |
| Shower Pan | 10/20/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 10/22/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/27/2021 | Approved | STEVEN BACK |
| Final | 10/27/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Approved | STEVEN BACK |
| Green Building Rough | 10/27/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 11/1/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 11/1/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 11/1/2021 | Approved | STEVEN BACK |
| Insulation | 11/1/2021 | Approved | STEVEN BACK |
| Final | 1/12/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 1/12/2022 | Approved | STEVEN BACK |
| Green Building Final | 1/12/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Gas Company | STEVEN BACK |
| Smoke Detectors | 1/12/2022 | Approved | STEVEN BACK |
| Final | 2/17/2022 | OK to Issue CofO | STEVEN BACK |
| HVAC-Final | 2/17/2022 | Approved | STEVEN BACK |