23655-23657 W HATTERAS ST 91367
Certificate Information: 23655-23657 W HATTERAS ST 91367
- Application / Permit
- 21014-20000-03333
- Plan Check / Job No.
- B21VN08477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16' x 31' ADDITION TO SINGLE FAMILY DWELLING; CONVERT 22' X 21'-5" ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- CofO Issued on 6/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | SELLA BENYAMIN |
| Corrections Issued | 8/10/2021 | SELLA BENYAMIN |
| Quality Review Completed | 8/13/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/13/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | SELLA BENYAMIN |
| Plan Check Approved | 11/5/2021 | SELLA BENYAMIN |
| Issued | 11/16/2021 | APPLICANT |
| CofO in Progress | 5/26/2022 | TROY SANDERS |
| Permit Finaled | 6/4/2022 | MICHAEL SMITH |
| CofO Issued | 6/4/2022 | MICHAEL SMITH |
| Permit Finaled | 6/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/22/2021 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 11/30/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 11/30/2021 | Approved | TROY SANDERS |
| Underground Mechanical | 11/30/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 1/3/2022 | Partial Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 1/3/2022 | Approved | TROY SANDERS |
| Green Building Rough | 1/3/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 1/3/2022 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 1/31/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 1/31/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 1/31/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 1/31/2022 | Approved | TROY SANDERS |
| Insulation | 2/8/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 2/22/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/25/2022 | Approved | TROY SANDERS |
| Final | 5/25/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 5/25/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/25/2022 | Approved | TROY SANDERS |