5805 N COLUMBUS AVE 91411
Certificate Information: 5805 N COLUMBUS AVE 91411
- Application / Permit
- 21014-20000-03330
- Plan Check / Job No.
- B21VN08474
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITIONS AND MAJOR REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- Issued on 3/22/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/3/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/27/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 2/24/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| Issued | 3/22/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | CARLOS AGUILERA |
| ZI | Cleared | 8/18/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 12/30/2021 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 1/3/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/12/2024 | Partial Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/29/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/9/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 5/9/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/2/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/26/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/18/2024 | Conditional Approval | RYAN SALAZAR |
| PLUMBING-Rough | 12/18/2024 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/12/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 2/12/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 2/12/2025 | Approved | RYAN SALAZAR |
| Insulation | 2/25/2025 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 3/5/2025 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 3/5/2025 | Approved | RYAN SALAZAR |