5649 N RAWLINGS AVE 91367

Certificate Information: 5649 N RAWLINGS AVE 91367

Application / Permit
21014-20000-03322
Plan Check / Job No.
B21VN08456
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXPAND (E) LIVING ROOM, (2) BEDROOMS, BATHROOMS & ENTRY, ADD (N) LAUNDRY ROOM ON 1ST FLR (IRR SHAPED) & ADD MASTER BEDROOM/BATHROOM ON 2ND FLOOR (IRR 35'-10" X 29'-3") OF (E) 1-STORY SFD W/ ATTACHED GARAGE; MAJOR REMODEL (NFPA-13D FIRE SPRINLERS THROUGHOUT)
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 11/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 NILOOFAR MEHRAIN
Corrections Issued 8/10/2021 NILOOFAR MEHRAIN
Quality Review Completed 8/13/2021 STEVEN KIM
Building Plans Picked Up 8/17/2021 APPLICANT
Applicant returned to address corrections 1/14/2022 NILOOFAR MEHRAIN
Plan Check Approved 1/24/2022 NILOOFAR MEHRAIN
Plan Check Approved 5/18/2022 NILOOFAR MEHRAIN
Issued 5/18/2022 APPLICANT
CofO in Progress 9/6/2023 ALEXANDER HANDY
Permit Finaled 11/27/2023 JOHN JANSON
CofO Issued 11/27/2023 JOHN JANSON
Permit Finaled 11/27/2023 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 10/25/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/8/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 11/24/2021 RUEL COLE
Low Impact Development Cleared 12/14/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 12/14/2021 CARLOS AGUILERA
GPI Written Notices Cleared 1/24/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 1/24/2022 NILOOFAR MEHRAIN
Hold Cleared 4/21/2022 JEREMY CORONEL

Contact Information

Contractor L A Home Construction Inc; Lic. No.: 1032013-B 5728 DELCO AVENUE      WOODLAND HILLS, CA 91367
Engineer Kazemi,, Milad; Lic. No.: C92143 21126 MERRIDY STREET      CHATSWORTH, CA 91311

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/20/2022 Approved STEVEN BACK
PLUMBING-Rough 5/20/2022 Partial Approval STEVEN BACK
Deputy Steel/Welding 5/24/2022 Conditional Approval STEVEN BACK
Deputy Steel/Welding 5/31/2022 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 6/6/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Corrections Issued STEVEN BACK
Deputy Drilled-In Anchors 7/12/2022 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Corrections Issued STEVEN BACK
Pre-Inspection 7/14/2022 Corrections Issued STEVEN BACK
HVAC-Rough 8/12/2022 Not Ready for Inspection STEVEN BACK
Pre-Inspection 8/12/2022 Partial Inspection STEVEN BACK
PLUMBING-Rough 8/25/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 9/22/2022 Approved STEVEN BACK
PLUMBING-Rough 9/22/2022 Approved STEVEN BACK
HVAC-Rough 10/5/2022 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 11/14/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Corrections Issued STEVEN BACK
HVAC-Rough 11/14/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 11/14/2022 Not Ready for Inspection STEVEN BACK
Deputy Wood Construction 11/15/2022 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 11/22/2022 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Approved STEVEN BACK
Green Building Rough 11/22/2022 Approved STEVEN BACK
HVAC-Final 11/22/2022 Corrections Issued STEVEN BACK
HVAC-Rough 11/22/2022 Approved STEVEN BACK
MERV13>=Rough 11/22/2022 Approved STEVEN BACK
Special/Order Compliance 11/22/2022 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 11/23/2022 Approved STEVEN BACK
Insulation 11/23/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 11/23/2022 Corrections Issued STEVEN BACK
Insulation 12/1/2022 Approved STEVEN BACK
Interior/Exterior Lathing 12/1/2022 Partial Approval STEVEN BACK
Drywall Nailing 12/13/2022 Approved ALEXANDER HANDY
Shower Pan 1/26/2023 Approved JESUS PINEDA
ELECTRICAL-Final 6/20/2023 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 6/23/2023 Corrections Issued HORACE FULTZ
HVAC-Final 6/23/2023 Not Ready for Inspection HORACE FULTZ
Gas Test 7/13/2023 Approved ALEXANDER HANDY
PLUMBING-Final 7/13/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 7/25/2023 Approved ALEXANDER HANDY
Service/Power Release 7/25/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/2/2023 SGSOV Not Ready ALEXANDER HANDY
ELECTRICAL-Final 9/5/2023 Approved ALEXANDER HANDY
Final 9/5/2023 OK to Issue CofO ALEXANDER HANDY
Green Building Final 9/5/2023 Approved ALEXANDER HANDY
HVAC-Final 9/5/2023 Approved ALEXANDER HANDY
MERV13>=Final 9/5/2023 Approved ALEXANDER HANDY
PLUMBING-Final 9/5/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Gas Company ALEXANDER HANDY
Smoke Detectors 9/5/2023 Approved ALEXANDER HANDY