13978 W REMINGTON ST 91331
Certificate Information: 13978 W REMINGTON ST 91331
- Application / Permit
- 21014-20000-03302
- Plan Check / Job No.
- B21VN08398
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E )20' x 20' GARAGE TO ACCESSORY DWELLING UNIT WITH 22'6"x 20' ADDITION PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP
- Permit Issued
- Issued on 10/29/2021
- Issuing Office
- Current Status
- Issued on 10/29/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | JEFFREY TANGONAN |
| Corrections Issued | 7/3/2021 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 10/21/2021 | JEFFREY TANGONAN |
| Issued | 10/29/2021 | APPLICANT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2021 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 10/15/2021 | SUNG JOON WON |
| Sewer availability | Cleared | 10/23/2021 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/21/2023 | Partial Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 5/16/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/16/2023 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/24/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/24/2023 | Approved | MICHEL ABAJAN |
| Gas Test | 7/24/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/24/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/24/2023 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 7/24/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/24/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 7/24/2023 | Approved | MICHEL ABAJAN |
| Insulation | 7/31/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/31/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 8/8/2023 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 1/25/2024 | Approved | MICHEL ABAJAN |
| Final | 1/25/2024 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/25/2024 | Approved | MICHEL ABAJAN |
| Green Building Final | 1/25/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/25/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/25/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 1/25/2024 | Approved | MICHEL ABAJAN |