14165 W GAIN ST 91331

Certificate Information: 14165 W GAIN ST 91331

Application / Permit
21014-20000-03297
Plan Check / Job No.
B21VN08381
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DET GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.3(c) & (d) W/ 15'X12'6" ADDITION. ALL WORK PER WFPP.
Permit Issued
Issued on 12/13/2021
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/23/2021 HAYATO TSUCHIYA
Corrections Issued 7/25/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 11/9/2021 HAYATO TSUCHIYA
Plan Check Approved 12/10/2021 HAYATO TSUCHIYA
Issued 12/13/2021 APPLICANT
Building Plans Picked Up 12/20/2021 APPLICANT
CofO in Progress 8/26/2022 MICHEL ABAJAN
Permit Finaled 9/3/2022 DEROLD HAUFF
CofO Issued 9/3/2022 DEROLD HAUFF
Permit Finaled 9/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/5/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/5/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/5/2021 LEE GUILBEAUX
Sewer availability Cleared 8/5/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/5/2021 LEE GUILBEAUX
Construction near power lines Cleared 10/25/2021 RIDWAN HARDY

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/11/2022 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 3/15/2022 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 3/21/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 3/21/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 4/1/2022 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 4/15/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/15/2022 Approved MICHEL ABAJAN
Green Building Rough 4/15/2022 Approved MICHEL ABAJAN
HVAC-Rough 4/15/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 4/15/2022 Approved MICHEL ABAJAN
Insulation 5/12/2022 Corrections Issued DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval MICHEL ABAJAN
Insulation 5/16/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/16/2022 Approved MICHEL ABAJAN
Shower Pan 6/28/2022 Approved ARAM AVEDISIAN
Gas Test 7/12/2022 Approved MICHEL ABAJAN
Sewer 7/12/2022 Approved MICHEL ABAJAN
Underground Mechanical 7/12/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 8/5/2022 Approved MICHEL ABAJAN
Drywall Nailing 8/26/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/26/2022 Approved MICHEL ABAJAN
Final 8/26/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 8/26/2022 Approved MICHEL ABAJAN
HVAC-Final 8/26/2022 Approved MICHEL ABAJAN
PLUMBING-Final 8/26/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 8/26/2022 Approved MICHEL ABAJAN