6450 N GREENBUSH AVE 91401

Certificate Information: 6450 N GREENBUSH AVE 91401

Application / Permit
21014-20000-03289
Plan Check / Job No.
B21VN08348
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (64'-0"x82'-5"), 3003 SQFT SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE (391 SQFT) AND OPEN TRELLIS AT REAR W/NFPA-13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/20/2022
Issuing Office
Current Status
CofO Issued on 6/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 PETER MOSESIAN
Corrections Issued 8/9/2021 PETER MOSESIAN
Quality Review Completed 8/18/2021 OMID HEDAYAT
Building Plans Picked Up 8/24/2021 APPLICANT
Plan Check Approved 4/4/2022 PETER MOSESIAN
Issued 4/20/2022 APPLICANT
CofO in Progress 6/14/2023 KIRK SANDERS
Permit Finaled 6/22/2023 MICHAEL SMITH
CofO Issued 6/22/2023 MICHAEL SMITH
Permit Finaled 6/22/2023 MICHAEL SMITH

Permit Application Clearance Information

Permit Cleared 9/13/2021 CARLOS AGUILERA
ZA Case Cleared 9/13/2021 MIGUEL GAMBOA
Sewer availability Cleared 11/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/29/2021 CARLOS AGUILERA
Low Impact Development Cleared 1/19/2022 CHRIS VONG
Hydrant and Access approval Cleared 1/28/2022 GILBERT URREA
Hydrant and Access approval Cleared 1/28/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 1/31/2022 CARLOS AGUILERA
Trees in Parkway Cleared 3/15/2022 ADALBERTO VERA

Contact Information

Contractor A P W Builders Inc; Lic. No.: 643803-B 5302 DENNY AVENUE #102 A      NORTH HOLLYWOOD, CA 91601
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/16/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 5/18/2022 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 5/19/2022 Conditional Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/8/2022 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 6/8/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 6/8/2022 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 6/8/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 6/15/2022 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 6/22/2022 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Corrections Issued RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Corrections Issued ALAN MORELOS
Deputy Wood Construction 9/19/2022 Conditional Approval RAFAEL CORTES
ELECTRICAL-Rough 9/20/2022 Approved RAFAEL CORTES
HVAC-Rough 9/20/2022 Approved RAFAEL CORTES
PLUMBING-Rough 9/20/2022 Approved RAFAEL CORTES
BUILDING-Rough-Frame 9/22/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 9/22/2022 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 9/22/2022 Not Ready for Inspection RAFAEL CORTES
BUILDING-Rough-Frame 10/7/2022 Partial Approval RAFAEL CORTES
Green Building Rough 10/7/2022 Not Ready for Inspection RAFAEL CORTES
Interior/Exterior Lathing 10/7/2022 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 10/7/2022 Approved RAFAEL CORTES
Insulation 10/12/2022 Partial Approval MISAEL ESPARZA
Drywall Nailing 10/19/2022 Not Ready for Inspection CALEB MEISTER
Green Building Rough 10/19/2022 Not Ready for Inspection CALEB MEISTER
Insulation 10/19/2022 Approved CALEB MEISTER
Drywall Nailing 10/26/2022 Conditional Approval MISAEL ESPARZA
Green Building Rough 10/26/2022 Not Ready for Inspection MISAEL ESPARZA
Sewer 11/4/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 11/30/2022 Approved KIRK SANDERS
Interior/Exterior Lathing 1/12/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/3/2023 Approved KIRK SANDERS
Drywall Nailing 5/3/2023 Approved KIRK SANDERS
Final 5/3/2023 Corrections Issued KIRK SANDERS
Gas Test 5/3/2023 Approved KIRK SANDERS
Green Building Final 5/3/2023 Not Ready for Inspection KIRK SANDERS
Green Building Rough 5/3/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Not Ready KIRK SANDERS
Service/Power Release 5/3/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 5/3/2023 Approved KIRK SANDERS
Final 5/25/2023 Corrections Issued KIRK SANDERS
Green Building Final 5/25/2023 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/25/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 5/25/2023 Not Ready for Inspection KIRK SANDERS
Final 6/2/2023 No Access for Inspection KIRK SANDERS
Green Building Final 6/2/2023 No Access for Inspection KIRK SANDERS
Service/Power Release 6/2/2023 No Access for Inspection KIRK SANDERS
Final 6/13/2023 OK to Issue CofO KIRK SANDERS
Green Building Final 6/13/2023 Approved KIRK SANDERS
Service/Power Release 6/13/2023 Approved KIRK SANDERS