7661 N CHIMINEAS AVE 91335

Certificate Information: 7661 N CHIMINEAS AVE 91335

Application / Permit
21014-20000-03282
Plan Check / Job No.
B21VN08335
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-2" X 20' DETACHED GARAGE AND ADD 18'-2" X 24'-7" TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/24/2022
Issuing Office
Current Status
CofO Issued on 8/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 6/30/2021 RAPHAEL ROSAS
Corrections Issued 7/1/2021 RAPHAEL ROSAS
Applicant returned to address corrections 8/26/2021 RAPHAEL ROSAS
Plan Check Approved 1/15/2022 RAPHAEL ROSAS
Building Plans Picked Up 1/26/2022 APPLICANT
Issued 3/24/2022 APPLICANT
CofO in Progress 8/12/2024 JEFFREY BULL
Permit Finaled 8/12/2024 JOHN JANSON
CofO Issued 8/12/2024 JOHN JANSON
Permit Finaled 8/12/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/6/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/23/2021 GABRIEL ROBLES
Sewer availability Cleared 8/23/2021 GABRIEL ROBLES
Low Impact Development Cleared 1/1/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/3/2022 JOHN LIN
Construction near power lines Cleared 1/15/2022 JOHN BACON

Contact Information

Contractor Owner-Builder       ,
Engineer Rahman,, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/21/2022 Approved JEFFREY BULL
PLUMBING-Rough 12/21/2022 Partial Approval JEFFREY BULL
Deputy Drilled-In Anchors 12/23/2022 Partial Approval JEFFREY BULL
Excavation/Setback/Form/Re-Bar 1/31/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 3/21/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 3/21/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 3/21/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/28/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 3/28/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 3/28/2023 Not Ready for Inspection JEFFREY BULL
Rough-Elec/Plmb/HVAC 5/19/2023 Approved JEFFREY BULL
Insulation 5/30/2023 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 5/30/2023 Partial Approval JEFFREY BULL
Drywall Nailing 6/15/2023 Approved VINCENT HANLEY
Sewer 7/3/2023 Approved JEFFREY BULL
Underground Mechanical 7/3/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 6/25/2024 Approved JEFFREY BULL
ELECTRICAL-Final 6/25/2024 Approved JEFFREY BULL
Final 6/25/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 6/25/2024 Approved JEFFREY BULL
Green Building Final 6/25/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 6/25/2024 Approved JEFFREY BULL
HVAC-Final 6/25/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Final 6/25/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 6/25/2024 Approved JEFFREY BULL
Smoke Detectors 6/25/2024 Approved JEFFREY BULL
Final 8/6/2024 Not Ready for Inspection TROY SANDERS
Green Building Final 8/6/2024 Approved TROY SANDERS
Final 8/12/2024 OK to Issue CofO JEFFREY BULL