10353 N WHITEGATE AVE 91040

Certificate Information: 10353 N WHITEGATE AVE 91040

Application / Permit
21014-20000-03272
Plan Check / Job No.
B21VN08310
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADDITION TO AN EXISTING DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2021 APPLICANT
Assigned to Plan Check Engineer 7/2/2021 CARLOS MONTES
Corrections Issued 7/5/2021 CARLOS MONTES
Applicant returned to address corrections 8/2/2021 CARLOS MONTES
Applicant returned to address corrections 8/9/2021 MONICA RAMIREZ
Plan Check Approved 8/11/2021 ZAW HAN
Issued 8/31/2021 APPLICANT
CofO in Progress 2/8/2023 DAVID ANDERSON
CofO Issued 3/4/2023 MICHAEL SMITH
Permit Finaled 3/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 7/9/2021 STEVEN WECHSLER
ZI Cleared 7/9/2021 STEVEN WECHSLER
Grading Pre-Inspection Cleared 7/26/2021 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 7/26/2021 CARLOS AGUILERA
Sewer availability Cleared 7/26/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/27/2021 CARLOS AGUILERA

Contact Information

Architect Atelier, La Design & Development Inc; Lic. No.: BUS10336 3902 EAST BLVD      LOS ANGELES, CA 90066
Architect Diradourian,, Richard C; Lic. No.: NA10336       ,
Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/8/2021 Partial Inspection WILLIAM KUEHN
Footing/Foundation/Slab 12/15/2021 Approved WILLIAM KUEHN
PLUMBING-Rough 12/15/2021 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 2/3/2022 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 2/3/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Approved MATTHEW NELSON
Green Building Rough 2/11/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 2/23/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 2/23/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Approved MATTHEW NELSON
HVAC-Rough 2/23/2022 Approved MATTHEW NELSON
PLUMBING-Rough 2/23/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/1/2022 Partial Approval GREGG CUMMINGS
Insulation 3/7/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 3/7/2022 Approved WILLIAM WREN
Drywall Nailing 3/14/2022 Corrections Issued WILLIAM WREN
Drywall Nailing 3/17/2022 Approved WILLIAM WREN
Green Building Final 9/19/2022 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 9/19/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 9/19/2022 Approved DAVID ANDERSON
Final 12/29/2022 Corrections Issued DAVID ANDERSON
Green Building Final 12/29/2022 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Not Ready DAVID ANDERSON
Final 2/7/2023 OK to Issue CofO DAVID ANDERSON
Green Building Final 2/7/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Approved DAVID ANDERSON