9132 N HAYVENHURST AVE 91343

Certificate Information: 9132 N HAYVENHURST AVE 91343

Application / Permit
21014-20000-03270
Plan Check / Job No.
B21VN08300
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E)18' X 20' DETACHED GARAGE AND ADD 18' X 25' TO CREATE DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ADD 11' X 19'-6" ATTACHED CARPORT. ALL WORK PER WFPP AND ENGINEERING DETAILS.
Permit Issued
Issued on 2/24/2022
Issuing Office
Current Status
CofO Issued on 7/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 6/30/2021 RAPHAEL ROSAS
Corrections Issued 7/1/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/10/2022 RAPHAEL ROSAS
Issued 2/24/2022 APPLICANT
Building Plans Picked Up 2/25/2022 APPLICANT
CofO in Progress 6/15/2022 ALAN MORELOS
Permit Finaled 7/5/2022 RONALD MYRICK
CofO Issued 7/5/2022 RONALD MYRICK
Permit Finaled 7/5/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 7/6/2021 CARLOS AGUILERA
Sewer availability Cleared 7/7/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 7/14/2021 PATRICK MISCHLICH
Low Impact Development Cleared 10/28/2021 LONDY ALVARADO
Eng Process Fee Ord 176,300 Cleared 11/4/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/29/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 1/31/2022 JOHN LIN
GPI Written Notices Cleared 2/9/2022 RAPHAEL ROSAS

Contact Information

Contractor Golden Construction Group Llc; Lic. No.: 1078364-B 16814 CITRONIA STREET      NORTHRIDGE, CA 91343

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/2/2022 Corrections Issued RAUL OLAGI
Pre-Inspection 3/11/2022 Corrections Issued RAUL OLAGI
Pre-Inspection 3/11/2022 Partial Inspection ALAN MORELOS
Sewer 3/16/2022 Conditional Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 3/22/2022 Approved ROBERT GOLD
Footing/Foundation/Slab 3/22/2022 Approved ROBERT GOLD
Pre-Inspection 3/22/2022 Approved ROBERT GOLD
ELECTRICAL-Rough 4/14/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Corrections Issued RAUL OLAGI
Green Building Rough 4/14/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 4/14/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 4/19/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 4/19/2022 Approved RAUL OLAGI
Green Building Rough 4/19/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 4/19/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 4/19/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 4/22/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Approved RAUL OLAGI
HVAC-Rough 4/22/2022 Approved RAUL OLAGI
PLUMBING-Rough 4/22/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 4/27/2022 Partial Approval RAUL OLAGI
Green Building Rough 4/27/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 4/27/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 4/27/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/2/2022 Approved RAUL OLAGI
Insulation 5/2/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/2/2022 Partial Approval RAUL OLAGI
Drywall Nailing 5/9/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/9/2022 Approved RAUL OLAGI
Final 6/1/2022 Corrections Issued RAUL OLAGI
Green Building Final 6/1/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/1/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 6/1/2022 Approved RAUL OLAGI
ELECTRICAL-Final 6/14/2022 Approved ALAN MORELOS
Final 6/14/2022 OK to Issue CofO ALAN MORELOS
HVAC-Final 6/14/2022 Approved ALAN MORELOS
PLUMBING-Final 6/14/2022 Approved ALAN MORELOS