1025 N LACHMAN LANE 90272

Certificate Information: 1025 N LACHMAN LANE 90272

Application / Permit
21014-20000-03265
Plan Check / Job No.
B21VN08287
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC: ADDITION AND INTERIOR AND EXTERIOR REMODEL. PER ENG. DESIGN
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 7/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 6/29/2021 JESSE ARELLANO
Corrections Issued 6/29/2021 JESSE ARELLANO
Applicant returned to address corrections 9/20/2021 JESSE ARELLANO
Applicant returned to address corrections 10/7/2021 JESSE ARELLANO
Plan Check Approved 10/8/2021 JESSE ARELLANO
Issued 10/20/2021 APPLICANT
Building Plans Picked Up 10/26/2021 APPLICANT
CofO in Progress 7/25/2023 GERMAN RODRIGUEZ MENDOZA
Permit Finaled 7/26/2023 DANIEL ORRANTE
CofO Issued 7/26/2023 DANIEL ORRANTE
Permit Finaled 7/26/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/13/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/15/2021 DINAH GARIN
Coastal Zone Cleared 8/20/2021 PABLO ESTRADA
ZI Cleared 8/20/2021 PABLO ESTRADA
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 9/20/2021 JESSE ARELLANO
Green Code Cleared 10/7/2021 JESSE ARELLANO

Contact Information

Contractor Neighborhood Home; Lic. No.: 638351-B 5410 BAYRIDGE      RANCHO PALOS VERDES, CA 90275

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2022 Approved ANDREW NAVE
Insulation 4/15/2022 Partial Approval ANDREW NAVE
PLUMBING-Rough 4/15/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 4/18/2022 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Approved ANDREW NAVE
Deputy Wood Construction 4/19/2022 Approved MICHAEL PELHAM
ELECTRICAL-Rough 4/20/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 4/22/2022 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Approved ANDREW NAVE
Green Building Rough 4/22/2022 Approved ANDREW NAVE
HVAC-Rough 4/22/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 4/22/2022 Partial Approval ANDREW NAVE
Insulation 4/25/2022 Conditional Approval ANDREW NAVE
Drywall Nailing 4/29/2022 Approved ANDREW NAVE
Insulation 5/3/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 5/3/2022 Approved ANDREW NAVE
Final 4/27/2023 Corrections Issued BRENDAN LOONEY
Green Building Final 4/27/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 4/27/2023 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 4/27/2023 Approved BRENDAN LOONEY
Final 7/20/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA