5847 N BEVIS AVE 91411
Certificate Information: 5847 N BEVIS AVE 91411
- Application / Permit
- 21014-20000-03255
- Plan Check / Job No.
- B21VN08240
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19'-7" X 14' ADDITION TO (E) SFD FOR NEW BEDROOM. INTERIOR REMODEL TO (E) BEDROOM. WORK PER WFPP.
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2021 | ROSENDO MEDINA |
| Corrections Issued | 6/29/2021 | ROSENDO MEDINA |
| Plan Check Approved | 7/19/2021 | ROSENDO MEDINA |
| Issued | 7/20/2021 | APPLICANT |
| Building Plans Picked Up | 7/20/2021 | APPLICANT |
| CofO in Progress | 9/22/2021 | RICHARD DOCKUS |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
| CofO Issued | 1/14/2023 | MICHAEL SMITH |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/12/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/12/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/26/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/26/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/5/2021 | Approved | MATTHEW NELSON |
| Wood Frame | 8/9/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2021 | Partial Approval | WILLIAM KUEHN |
| Green Building Rough | 8/12/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2021 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 8/24/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 8/24/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 8/24/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 8/24/2021 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 8/26/2021 | Approved | RICHARD DOCKUS |
| Insulation | 8/26/2021 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 8/27/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/10/2021 | Approved | RICHARD DOCKUS |
| Final | 9/10/2021 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 9/10/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 9/10/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 9/10/2021 | Corrections Issued | RICHARD DOCKUS |
| Final | 9/16/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 9/16/2021 | Approved | RICHARD DOCKUS |
| Final | 9/21/2021 | OK to Issue CofO | RICHARD DOCKUS |