17916 W ERWIN ST 91316

Certificate Information: 17916 W ERWIN ST 91316

Application / Permit
21014-20000-03254
Plan Check / Job No.
B21VN08233
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 29'-6" X 31' IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/29/2021
Issuing Office
Current Status
Issued on 11/29/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/25/2021 APPLICANT
Assigned to Plan Check Engineer 6/25/2021 RAPHAEL ROSAS
Corrections Issued 6/26/2021 RAPHAEL ROSAS
Applicant returned to address corrections 10/28/2021 RAPHAEL ROSAS
Applicant returned to address corrections 11/17/2021 RAPHAEL ROSAS
Issued 11/29/2021 APPLICANT
Building Plans Picked Up 11/30/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/5/2021 GABRIEL ROBLES
"T" removal Cleared 10/5/2021 STEVEN WECHSLER
Miscellaneous Cleared 10/5/2021 STEVEN WECHSLER
ZI Cleared 10/5/2021 STEVEN WECHSLER
Roof/Waste drainage to street Cleared 11/18/2021 CARLOS AGUILERA
Sewer availability Cleared 11/20/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/10/2021 Approved SEAN HAUPT
Special/Order Compliance 12/14/2021 No Access for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/16/2021 Partial Approval SEAN HAUPT
Insulation 12/16/2021 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 12/16/2021 Approved SEAN HAUPT
Underground Mechanical 12/16/2021 Approved SEAN HAUPT
Wood Frame 12/16/2021 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Corrections Issued SEAN HAUPT
Rough-Elec/Plmb/HVAC 1/18/2022 Not Ready for Inspection SEAN HAUPT
Wood Frame 1/18/2022 Corrections Issued SEAN HAUPT
BUILDING-Rough-Frame 1/20/2022 Approved SEAN HAUPT
Green Building Rough 1/20/2022 Not Ready for Inspection SEAN HAUPT
Insulation 1/20/2022 Not Ready for Inspection SEAN HAUPT
Insulation 1/24/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 1/24/2022 Approved SEAN HAUPT
Drywall Nailing 1/28/2022 Approved ROBERT GOLD
Interior/Exterior Lathing 1/28/2022 Not Ready for Inspection ROBERT GOLD
Shower Pan 1/28/2022 Approved ROBERT GOLD
Interior/Exterior Lathing 1/31/2022 Approved JUSTIN HAWLEY
Shower Pan 1/31/2022 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 3/31/2022 Approved SEAN HAUPT
Final 3/31/2022 Corrections Issued SEAN HAUPT
Green Building Final 3/31/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 3/31/2022 Approved SEAN HAUPT
PLUMBING-Final 3/31/2022 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/31/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 3/31/2022 Approved SEAN HAUPT