12833 W CHALON ROAD 90049
Certificate Information: 12833 W CHALON ROAD 90049
- Application / Permit
- 21014-20000-03245
- Plan Check / Job No.
- B21VN08193
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & ADDITION TO (E) SFD BY CONVERTING (E) ATT. GARAGE INTO LIVING AREA 948 SQFT AND ADDITION TO 2ND FLOOR WORKOUT ROOM. W/NFPA 13D SPRINKLERS REQ THROUGHOUT
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- CofO Issued on 10/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | PETER MOSESIAN |
| Corrections Issued | 7/10/2021 | PETER MOSESIAN |
| Quality Review Completed | 7/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/20/2021 | APPLICANT |
| Plan Check Approved | 1/10/2022 | PETER MOSESIAN |
| Issued | 1/10/2022 | APPLICANT |
| CofO in Progress | 5/31/2023 | KEVIN SARGSYAN |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
| CofO Issued | 10/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 7/26/2021 | MIGUEL GAMBOA |
| BHO/Hillside ordinance | Cleared | 7/29/2021 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 7/29/2021 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 7/29/2021 | NIKTA MOUSAVI |
| BHO/Hillside ordinance | Cleared | 7/29/2021 | NIKTA MOUSAVI |
| Watercourse | Cleared | 8/2/2021 | MAHELET GEBEYHU |
| Private street | Cleared | 8/3/2021 | MIGUEL GAMBOA |
| BHO/Hillside ordinance | Cleared | 8/4/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | NIKTA MOUSAVI |
| Low Impact Development | Cleared | 12/21/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/3/2022 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 1/10/2022 | PETER MOSESIAN |
Contact Information
| Architect | Mccarthy,, Dion P; Lic. No.: C26044 | DESIGNARC 10524 ILONA AVE. LOS ANGELES, CA 90064 |
| Contractor | Ceci Clarke Inc; Lic. No.: 1040135-B | 444 ARNEILL ROAD CAMARILLO, CA 93010 |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
| Landscape Architect | Eriksson,, Nord Jon; Lic. No.: LA2858 | 844 E. GREEN STREET STE 201 PASADENA, CA 91101 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/28/2022 | Partial Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 2/28/2022 | Corrections Issued | JOHN KIDWELL |
| Pre-Inspection | 3/2/2022 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 4/15/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 4/15/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 4/21/2022 | No Access for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 4/27/2022 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/9/2022 | Partial Approval | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 5/9/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 5/9/2022 | Partial Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 5/9/2022 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 5/16/2022 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 5/16/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/6/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 6/6/2022 | Approved | JUAN VALENZUELA |
| Insulation | 6/6/2022 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 6/6/2022 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 6/10/2022 | Corrections Issued | JUAN VALENZUELA |
| Drywall Nailing | 6/14/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/28/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/25/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/4/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Final | 12/21/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 2/2/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/13/2023 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/1/2023 | Approved | KEVIN SARGSYAN |
| Green Building Final | 3/1/2023 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 3/1/2023 | Approved | KEVIN SARGSYAN |
| Final | 4/5/2023 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 5/30/2023 | OK to Issue CofO | KEVIN SARGSYAN |