5836 N NORWICH AVE 91411

Certificate Information: 5836 N NORWICH AVE 91411

Application / Permit
21014-20000-03243
Plan Check / Job No.
B21VN08187
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
43' X 16'-6" ADDITION OF A MASTER SUITE AND ENCLOSE 5' X 20' PORCH AND CONVERT TO LIVABLE SPACE TO THE (E) SINGLE FAMILY DWELLING..
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
Issued on 4/28/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/25/2021 APPLICANT
Assigned to Plan Check Engineer 6/25/2021 SERGIO MUNIZ
Corrections Issued 6/27/2021 SERGIO MUNIZ
Applicant returned to address corrections 3/16/2022 SERGIO MUNIZ
Plan Check Approved 4/13/2022 SERGIO MUNIZ
Building Plans Picked Up 4/13/2022 APPLICANT
Issued 4/28/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/2/2021 GABRIEL ROBLES
Sewer availability Cleared 8/2/2021 GABRIEL ROBLES
Low Impact Development Cleared 2/9/2022 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 2/15/2022 AMIR KASHFI

Contact Information

Contractor Gaz Construction; Lic. No.: 531868-B 11370 DONA DOROTEA DR      STUDIO CITY, CA 91604
Engineer Garza,, Omar Leonel; Lic. No.: S5593 600 WILSHIRE BLVD 760      LOS ANGELES, CA 90017

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/13/2022 Conditional Approval RICHARD DOCKUS
Footing/Foundation/Slab 9/15/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 9/26/2022 Partial Approval RICHARD DOCKUS
Wood Frame 9/26/2022 Partial Approval RICHARD DOCKUS
Deputy Drilled-In Anchors 11/2/2022 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/14/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/14/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 2/14/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 2/14/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/14/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/23/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 2/23/2023 Approved RYAN SALAZAR
Green Building Rough 2/23/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 2/23/2023 Approved RYAN SALAZAR
PLUMBING-Rough 2/23/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/7/2023 Partial Approval RYAN SALAZAR
Shower Pan 3/7/2023 Approved RYAN SALAZAR
Drywall Nailing 3/13/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/5/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 3/28/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 3/28/2024 Approved RYAN SALAZAR
Final 3/28/2024 Corrections Issued RYAN SALAZAR
Green Building Final 3/28/2024 Approved RYAN SALAZAR
Green Building Rough 3/28/2024 Approved RYAN SALAZAR
HVAC-Final 3/28/2024 Approved RYAN SALAZAR
PLUMBING-Final 3/28/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 3/28/2024 Approved RYAN SALAZAR
Smoke Detectors 3/28/2024 Approved RYAN SALAZAR