11591 W CUMPSTON ST 91601
Certificate Information: 11591 W CUMPSTON ST 91601
- Application / Permit
- 21014-20000-03218
- Plan Check / Job No.
- B21VN08086
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 13'-2" X 20'-0" ADDITION OF A BEDROOM AND CLOSET TO THE (E) SFD. ALL WORK PER WFPP AND ENGINEERING.
- Permit Issued
- Issued on 2/7/2022
- Issuing Office
- Current Status
- Issued on 2/7/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 6/26/2021 | ARTIN ZARUKIAN |
| Issued | 2/7/2022 | APPLICANT |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/12/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/12/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 12/14/2021 | RIDWAN HARDY |
Contact Information
| Contractor | All Construction Services; Lic. No.: 1056091-B | 9018 BALBOA BLVD #509 NORTHRIDGE, CA 91325 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/26/2022 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 8/31/2022 | Approved | THOMAS FINNILA |
| Wood Frame | 8/31/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Partial Approval | CALEB MEISTER |
| Interior/Exterior Lathing | 9/21/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 9/22/2022 | No Access for Inspection | CALEB MEISTER |
| Insulation | 9/26/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 9/30/2022 | Conditional Approval | CALEB MEISTER |
| Green Building Rough | 9/30/2022 | Conditional Approval | CALEB MEISTER |