15513 W ANDRAE CT 91343
Certificate Information: 15513 W ANDRAE CT 91343
- Application / Permit
- 21014-20000-03216
- Plan Check / Job No.
- B21VN08074
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 20'-8" X 47'-3" IRREGULAR SHAPED ADDITION TO (E) SFD.
- Permit Issued
- Issued on 8/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/5/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 8/18/2021 | APPLICANT |
| Applicant returned to address corrections | 5/27/2022 | OMAR GARNICA |
| Plan Check Approved | 6/1/2022 | OMAR GARNICA |
| Issued | 8/8/2022 | APPLICANT |
| CofO in Progress | 4/7/2023 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/10/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/25/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/28/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/28/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/29/2022 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 8/31/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/6/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 9/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 9/29/2022 | No Access for Inspection | GREGG CUMMINGS |
| MERV13>=Rough | 9/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 10/5/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/13/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/13/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 10/13/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 10/13/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/13/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/17/2022 | Approved | WILLIAM WREN |
| Final | 10/17/2022 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 10/17/2022 | Approved | WILLIAM WREN |
| Insulation | 11/1/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 11/1/2022 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 11/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 11/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/30/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/30/2022 | Approved | GREGG CUMMINGS |
| Final | 2/22/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/22/2023 | Approved | GREGG CUMMINGS |
| MERV13>=Final | 2/22/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 2/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 3/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 3/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 3/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 3/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/23/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Final | 4/7/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 4/7/2023 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |