724 W 140TH ST 90247
Certificate Information: 724 W 140TH ST 90247
- Application / Permit
- 21014-20000-03215
- Plan Check / Job No.
- B21VN08073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 30' X 21' ADDITION TO AND CONVERT THE (E) 20' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2021 | PARISA ZAHABI |
| Corrections Issued | 7/27/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 1/11/2022 | ALFREDO JARA |
| Plan Check Approved | 1/28/2022 | ANGELICA MARTINEZ |
| Issued | 3/1/2022 | APPLICANT |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| CofO in Progress | 11/2/2022 | JOHN KLARIN |
| Permit Finaled | 11/2/2022 | RONALD MYRICK |
| Permit Finaled | 11/2/2022 | RONALD MYRICK |
| CofO Issued | 11/2/2022 | RONALD MYRICK |
Permit Application Clearance Information
| ZI | Cleared | 7/29/2021 | DANG NGUYEN |
| Address approval | Cleared | 7/30/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 8/3/2021 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 9/20/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 11/30/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/28/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/29/2021 | JOSE HERNANDEZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Moreno General Services Inc; Lic. No.: 879426-B | 14340 ELSWORTH STREET STE 103 MORENO VALLEY, CA 92553 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/18/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| METHANE-Rough | 3/21/2022 | Corrections Issued | JOHN KLARIN |
| Deputy Drilled-In Anchors | 3/23/2022 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 4/7/2022 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 4/7/2022 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Barrier | 4/7/2022 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 4/7/2022 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 4/13/2022 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 4/13/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Partial Approval | EUGENE CASSIDY |
| Sewer | 5/23/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/5/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 7/5/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 7/5/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/5/2022 | Approved | JOHN KLARIN |
| MERV13>=Rough | 7/5/2022 | Approved | JOHN KLARIN |
| METHANE-Rough | 7/5/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/5/2022 | Approved | JOHN KLARIN |
| Insulation | 7/7/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 7/13/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/22/2022 | Approved | RYAN SALAZAR |
| Final | 9/27/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 9/27/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 9/27/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/27/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/11/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/11/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | EUGENE CASSIDY |
| Final | 10/18/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 10/25/2022 | Corrections Issued | JOHN KLARIN |
| Final | 11/2/2022 | OK to Issue CofO | JOHN KLARIN |