9840 N NATICK AVE 91343
Certificate Information: 9840 N NATICK AVE 91343
- Application / Permit
- 21014-20000-03206
- Plan Check / Job No.
- B21VN08056
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU. CONVERT EXISTING GARAGE (333 sq ft) TO 1 STORY ADU WITH PATIO COVER (120 sq ft) PER PER LAMC 12.22 A.33(c) AND (d) AND PR WFPP
- Permit Issued
- Issued on 9/29/2021
- Issuing Office
- Current Status
- CofO Issued on 10/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | JOE VO |
| Corrections Issued | 6/24/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/28/2021 | JOE VO |
| Issued | 9/29/2021 | APPLICANT |
| CofO in Progress | 9/20/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 10/27/2022 | MICHAEL SMITH |
| CofO Issued | 10/27/2022 | MICHAEL SMITH |
| Permit Finaled | 10/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/6/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/6/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/6/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/9/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 12/28/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/10/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 2/10/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/22/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 2/22/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 4/12/2022 | Corrections Issued | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/21/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 4/21/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/21/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 4/21/2022 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 4/21/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/6/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/6/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/6/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/6/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/6/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/13/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/13/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 5/26/2022 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 6/10/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/30/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Approved | JENNIFER RABUCHIN |
| Final | 8/30/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/30/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/30/2022 | Approved | JENNIFER RABUCHIN |
| Final | 9/13/2022 | OK to Issue CofO | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 9/15/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/15/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/15/2022 | Approved | JENNIFER RABUCHIN |