6457-6459 N NEDDY AVE 91307
Certificate Information: 6457-6459 N NEDDY AVE 91307
- Application / Permit
- 21014-20000-03187
- Plan Check / Job No.
- B21VN08010
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO LAUNDRY ROOM AND JUNIOR ACCESSORY DWELLING UNIT (385 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22 AND 22'-3" X 18'-7" IRREG SHAPED ADDITION FOR NEW BEDROOM, BATHROOM AND CLOSET. REMODEL KITCHEN AND REMOVE WALL BETWEEN LIVING ROOM AND KITCHEN.
- Permit Issued
- Issued on 8/4/2021
- Issuing Office
- Current Status
- CofO Issued on 11/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 7/21/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/4/2021 | JEROME MAGAT PALMA |
| Issued | 8/4/2021 | APPLICANT |
| Building Plans Picked Up | 8/5/2021 | APPLICANT |
| CofO in Progress | 11/9/2022 | TROY SANDERS |
| Permit Finaled | 11/21/2022 | JOHN JANSON |
| CofO Issued | 11/21/2022 | JOHN JANSON |
| Permit Finaled | 11/21/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/23/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | J M A General Contractor; Lic. No.: 893018-B | 5817 MCDONIE AVENUE WOODLAND HILLS, CA 91367 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/11/2021 | Partial Approval | TROY SANDERS |
| Sewer | 8/11/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 8/16/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 9/13/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 9/13/2021 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 9/17/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 9/17/2021 | Approved | TROY SANDERS |
| Green Building Rough | 9/17/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 9/17/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/17/2021 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 9/17/2021 | Approved | TROY SANDERS |
| Shower Pan | 10/1/2021 | Approved | TROY SANDERS |
| Insulation | 10/13/2021 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 10/13/2021 | Partial Approval | JESUS PINEDA |
| Insulation | 10/20/2021 | Approved | JESUS PINEDA |
| Drywall Nailing | 10/27/2021 | Approved | JESUS PINEDA |
| Final | 2/25/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 2/25/2022 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 2/25/2022 | Approved | TROY SANDERS |
| Final | 6/24/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 6/24/2022 | Approved | DAVID SCANTLIN |
| Final | 11/9/2022 | OK to Issue CofO | TROY SANDERS |